Transmission lines
- Puller and tensionerCoordinate the two ends of the stringing operation.
- Conductor reelTrack reel identity and released length by stringing section.
- Tower hardwareVerify the section geometry and hardware records before handover.
Construction and release sequence
- Confirm route access, crossings and structure locations
- Construct foundations and erect structures by section
- String, sag and clip conductors or install the underground circuit
- Reconcile clearances, circuit records and section release
Work packages and conformance checks
Conductor Stringing & HardwareCheck the surveyed conductor profile and crossing clearances at the recorded observation conditions.Transmission Structures & FoundationsSurvey tower centre, stub geometry, foundation levels and final tower alignment.HV Underground Cable — the Overhead-Line AlternativeSurvey duct runs, bend geometry, joint bays and cover before backfilling.
Production and measurement
Keep route-km and conductor-km distinct. Track crossings, drum changes and possession limits.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.TL.001 | Form access track - flat to undulating (grade <1:8) | m/day (dozer+grader crew) | 150 | 400 | 800 | S-065 |
| PRD.TL.002 | Form access track - steep benched (grade 1:8 to 1:4) | m/day | 40 | 120 | 250 | S-065 |
| PRD.TL.003 | Form access track - rock/extreme (rip or hammer/blast) | m/day | 10 | 40 | 100 | S-065 |
| PRD.TL.004 | Construct structure pad + crane hardstand (good ground, flat) | pads/crew-day | 0.5 | 1 | 2 | S-065 |
| PRD.TL.005 | Engineered crane hardstand capping place & compact | m2/day | 150 | 400 | 800 | S-065 |
| PRD.TL.006 | Imported capping / select fill placement | m3/day (per excavator+roller) | 200 | 500 | 1000 | S-065 |
| PRD.TL.007 | Easement clearing & mulching - light/medium vegetation | ha/day (mulcher crew) | 1 | 3 | 6 | S-065 |
| PRD.TL.008 | Easement clearing - heavy timber, excavator + cart | ha/day | 0.3 | 1 | 2.5 | S-065 |
| PRD.TL.009 | Stump grubbing at structure/track footprints | stumps/day | 20 | 60 | 120 | S-065 |
| PRD.TL.010 | Pad-and-chimney footing complete (good soil) - excavate, reo, pour, backfill | structures/crew-week | 1 | 2 | 4 | S-065 |
| PRD.TL.011 | Bored cast-in-situ pile drilling - soil | m/rig-day | 15 | 30 | 60 | S-065 |
| PRD.TL.012 | Bored pile rock socket (extra over soil) | m/rig-day | 2 | 6 | 15 | S-065 |
| PRD.TL.013 | Foundation concrete place (pump from agitators) | m3/hr | 15 | 30 | 50 | S-065 |
| PRD.TL.014 | Rock anchor drill, grout & proof-test | anchors/crew-day | 2 | 5 | 10 | S-065 |
| PRD.TL.015 | Lattice tower ground assembly (suspension, panelised) | t-assembled/crew-day | 3 | 6 | 12 | S-065 |
| PRD.TL.016 | Lattice tower full assembly+erect combined | structures/crew-week | 1 | 2 | 3 | S-065 |
| PRD.TL.017 | Pole dressing (cross-arms, arms, fittings) | poles/crew-day | 2 | 5 | 10 | S-065 |
| PRD.TL.018 | Lattice tower erection by crane (suspension, good access) | towers/crew-day | 0.3 | 0.7 | 1.5 | S-065 |
| PRD.TL.019 | Steel/concrete pole erection (set & plumb) | poles/crew-day | 1 | 3 | 6 | S-065 |
| PRD.TL.020 | Helicopter tower/section placement (on-station) | lifts/flying-hour | 4 | 8 | 15 | S-065 |
| PRD.TL.021 | Gin-pole erection (no-crane site) | towers/crew-week | 0.5 | 1 | 2 | S-065 |
| PRD.TL.022 | Tension stringing - pull-in phase conductor (open country) | conductor-km/crew-day | 1 | 3 | 6 | S-065 |
| PRD.TL.023 | Sag, tension & clip-in conductor | conductor-km/crew-day | 0.5 | 1.5 | 4 | S-065 |
| PRD.TL.024 | OPGW / earthwire stringing | km/crew-day | 1 | 2.5 | 5 | S-065 |
| PRD.TL.025 | Stringing across a crossing (road/rail/river) | crossings/day | 0.5 | 1 | 3 | S-065 |
| PRD.TL.026 | Fit dampers / bundle spacers / mid-span joints | fittings/crew-day | 20 | 50 | 100 | S-065 |
| PRD.TL.027 | Install structure earthing (driven electrodes + down-lead bond) | structures/crew-day | 2 | 5 | 10 | S-065 |
| PRD.TL.028 | Install buried counterpoise (trench, lay, weld, backfill) | m/crew-day | 100 | 300 | 600 | S-065 |
| PRD.TL.029 | Footing-resistance test per structure | structures/day | 8 | 20 | 40 | S-065 |
| PRD.TL.030 | Pre-energisation clearance / sag survey (LiDAR) | route-km/day | 5 | 15 | 40 | S-065 |
| PRD.TL.031 | OPGW OTDR end-to-end test & splice report | route-km/day | 10 | 30 | 60 | S-065 |
| PRD.TL.032 | Pre-energisation line patrol (visual/drone) | route-km/day | 5 | 20 | 50 | S-065 |
Construction references
- Overhead Transmission Line Construction
- Reconductoring and Live-Corridor Crossings
- HV Underground Cable Construction