Discipline library

Transmission lines

Verify tower and crossing control, release foundations and structures, then string and survey spans. Underground cable sections have separate duct and joint-bay releases.

Transmission lines
  1. Puller and tensionerCoordinate the two ends of the stringing operation.
  2. Conductor reelTrack reel identity and released length by stringing section.
  3. Tower hardwareVerify the section geometry and hardware records before handover.
Illustrative workfront within Transmission lines.
Open the Overhead conductor stringing section calculator

Construction and release sequence

  1. Confirm route access, crossings and structure locations
  2. Construct foundations and erect structures by section
  3. String, sag and clip conductors or install the underground circuit
  4. Reconcile clearances, circuit records and section release

Work packages and conformance checks

Production and measurement

Keep route-km and conductor-km distinct. Track crossings, drum changes and possession limits.

View the discipline reference figureTransmission lines reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.TL.001Form access track - flat to undulating (grade <1:8)m/day (dozer+grader crew)150400800S-065
PRD.TL.002Form access track - steep benched (grade 1:8 to 1:4)m/day40120250S-065
PRD.TL.003Form access track - rock/extreme (rip or hammer/blast)m/day1040100S-065
PRD.TL.004Construct structure pad + crane hardstand (good ground, flat)pads/crew-day0.512S-065
PRD.TL.005Engineered crane hardstand capping place & compactm2/day150400800S-065
PRD.TL.006Imported capping / select fill placementm3/day (per excavator+roller)2005001000S-065
PRD.TL.007Easement clearing & mulching - light/medium vegetationha/day (mulcher crew)136S-065
PRD.TL.008Easement clearing - heavy timber, excavator + cartha/day0.312.5S-065
PRD.TL.009Stump grubbing at structure/track footprintsstumps/day2060120S-065
PRD.TL.010Pad-and-chimney footing complete (good soil) - excavate, reo, pour, backfillstructures/crew-week124S-065
PRD.TL.011Bored cast-in-situ pile drilling - soilm/rig-day153060S-065
PRD.TL.012Bored pile rock socket (extra over soil)m/rig-day2615S-065
PRD.TL.013Foundation concrete place (pump from agitators)m3/hr153050S-065
PRD.TL.014Rock anchor drill, grout & proof-testanchors/crew-day2510S-065
PRD.TL.015Lattice tower ground assembly (suspension, panelised)t-assembled/crew-day3612S-065
PRD.TL.016Lattice tower full assembly+erect combinedstructures/crew-week123S-065
PRD.TL.017Pole dressing (cross-arms, arms, fittings)poles/crew-day2510S-065
PRD.TL.018Lattice tower erection by crane (suspension, good access)towers/crew-day0.30.71.5S-065
PRD.TL.019Steel/concrete pole erection (set & plumb)poles/crew-day136S-065
PRD.TL.020Helicopter tower/section placement (on-station)lifts/flying-hour4815S-065
PRD.TL.021Gin-pole erection (no-crane site)towers/crew-week0.512S-065
PRD.TL.022Tension stringing - pull-in phase conductor (open country)conductor-km/crew-day136S-065
PRD.TL.023Sag, tension & clip-in conductorconductor-km/crew-day0.51.54S-065
PRD.TL.024OPGW / earthwire stringingkm/crew-day12.55S-065
PRD.TL.025Stringing across a crossing (road/rail/river)crossings/day0.513S-065
PRD.TL.026Fit dampers / bundle spacers / mid-span jointsfittings/crew-day2050100S-065
PRD.TL.027Install structure earthing (driven electrodes + down-lead bond)structures/crew-day2510S-065
PRD.TL.028Install buried counterpoise (trench, lay, weld, backfill)m/crew-day100300600S-065
PRD.TL.029Footing-resistance test per structurestructures/day82040S-065
PRD.TL.030Pre-energisation clearance / sag survey (LiDAR)route-km/day51540S-065
PRD.TL.031OPGW OTDR end-to-end test & splice reportroute-km/day103060S-065
PRD.TL.032Pre-energisation line patrol (visual/drone)route-km/day52050S-065