Supplier information to obtain
Request the stringing schedule, section lengths, drum plan, conductor and bundle arrangement, crossing windows and matched equipment proposal.
Compare section boundaries against access to drum stands and machinery, crossings, drum lengths and approved conductor configuration.
Request the stringing schedule, section lengths, drum plan, conductor and bundle arrangement, crossing windows and matched equipment proposal.
Puller, tensioner, drum stands, pilot rope, travellers and clipping crews. Identify crossing protection and restricted-access support separately.
The PT2450 is an example of equipment configured for conductor pulling or tensioning. Condux Tesmec PT2450
Release structures and approved crossing arrangements, then mobilise the spread to agreed pull and tension sites.
Prepare each section, complete the pull and allow the occupation time for sagging, clipping and releasing the spread under the adopted sequence.
Reconcile accepted conductor length to drums and circuit configuration. Track route length separately from conductor length.
Batch quantity is installed conductor-km for one pull. A 2 km route section with two conductors installed together yields 4 conductor-km. Use timings for that same pull configuration.
One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Use the linked discipline reference and obtain a measured cycle for this specific configuration. The work package has no adopted numerical benchmark.
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.