Transmission lines

Overhead conductor stringing section

Transmission lines
  1. Puller and tensionerCoordinate the two ends of the stringing operation.
  2. Conductor reelTrack reel identity and released length by stringing section.
  3. Tower hardwareVerify the section geometry and hardware records before handover.
Illustrative workfront for Overhead conductor stringing section.

Hydraulic conductor puller-tensioner

Compare section boundaries against access to drum stands and machinery, crossings, drum lengths and approved conductor configuration.

Supplier information to obtain

Request the stringing schedule, section lengths, drum plan, conductor and bundle arrangement, crossing windows and matched equipment proposal.

Supporting plant and crew

Puller, tensioner, drum stands, pilot rope, travellers and clipping crews. Identify crossing protection and restricted-access support separately.

The PT2450 is an example of equipment configured for conductor pulling or tensioning. Condux Tesmec PT2450

Construction method

Release the workfront

Release structures and approved crossing arrangements, then mobilise the spread to agreed pull and tension sites.

Execute the work

Prepare each section, complete the pull and allow the occupation time for sagging, clipping and releasing the spread under the adopted sequence.

Measure and hand over

Reconcile accepted conductor length to drums and circuit configuration. Track route length separately from conductor length.

Productivity calculator

Batch quantity is installed conductor-km for one pull. A 2 km route section with two conductors installed together yields 4 conductor-km. Use timings for that same pull configuration.

Example values demonstrate the arithmetic. Use shift records, supplier programmes or a measured trial for an estimate.

Calculation basis and shift treatment

One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.

Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.

Productivity evidence

Use the linked discipline reference and obtain a measured cycle for this specific configuration. The work package has no adopted numerical benchmark.

Related methodologies

The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.

Discipline work packages and survey requirements