Discipline library

Underground mining

Transfer control to headings, record surveyed advance and support inspections, and manage mucking and services by released reach.

Underground mining
  1. Loader bucketMeasure accepted muck volume or tonnes on a consistent basis.
  2. Haul driveTravel, congestion and available ventilation affect cycles.
  3. Discharge pointReconcile dumped material to the receiving location.
Illustrative workfront within Underground mining.
Open the Load–haul–dump mucking to an ore pass calculator

Construction and release sequence

  1. Confirm survey control, ventilation and work-area access
  2. Advance and survey development reaches with their support crews
  3. Install services and reconcile muck destinations or backfill volumes
  4. Release supported reaches and reconcile dispatch and survey records

Work packages and conformance checks

Production and measurement

Model tramming distances, tip availability and service moves separately from heading advance.

View the discipline reference figureUnderground mining reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.UM.003Shaft sinking — conventional drill/blast/muck/line (advance)m/day123S-070
PRD.UM.004Raisebore raise (vent/ore/services) — reamm/day51015S-070
PRD.UM.005Production stoping (long-hole) — drill, charge, fire (ore)t/shift2006001500S-070
PRD.UM.006Pattern rock / friction bolt + plate — install & tensionbolts/shift203550S-070
PRD.UM.007Cable bolt — drill, install, grout & plateholes/shift102030S-070
PRD.UM.008Weldmesh & fibre-reinforced shotcrete to back / wallsm³/shift102030S-070
PRD.UM.009LHD bogging / loading to ore pass or truckt/hr50120200S-070
PRD.UM.010Backfill placement — paste / CAF / rockfill to mined voidm³/hr2050100S-070
PRD.UM.011Ventilation ducting / layflat ventbag run — hangm/shift100250500S-070
PRD.UM.012Services reticulation — water/air pipe + power/comms cablem/shift50150350S-070
PRD.UM.013Secondary breaking / oversize reduction (rockbreaker)t/hr2050120S-070
PRD.UM.014Shaft furnishing — guides/buntons, services, ladderwaym/day136S-070