Underground mining
- Loader bucketMeasure accepted muck volume or tonnes on a consistent basis.
- Haul driveTravel, congestion and available ventilation affect cycles.
- Discharge pointReconcile dumped material to the receiving location.
Construction and release sequence
- Confirm survey control, ventilation and work-area access
- Advance and survey development reaches with their support crews
- Install services and reconcile muck destinations or backfill volumes
- Release supported reaches and reconcile dispatch and survey records
Work packages and conformance checks
Underground development and advance surveySurvey excavation advance, grade and clearance profile from underground control by heading.Underground Ground Support — rock bolts, mesh & shotcreteMap installed support by chainage, row and observed excavation profile.Underground materials handling and backfillCompare cavity surveys, fill limits and material destinations against the production block model.Ventilation, Services, Dewatering & Shaft AccessTransfer control down the shaft and check installed services against the access clearance envelope.
Production and measurement
Model tramming distances, tip availability and service moves separately from heading advance.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.UM.003 | Shaft sinking — conventional drill/blast/muck/line (advance) | m/day | 1 | 2 | 3 | S-070 |
| PRD.UM.004 | Raisebore raise (vent/ore/services) — ream | m/day | 5 | 10 | 15 | S-070 |
| PRD.UM.005 | Production stoping (long-hole) — drill, charge, fire (ore) | t/shift | 200 | 600 | 1500 | S-070 |
| PRD.UM.006 | Pattern rock / friction bolt + plate — install & tension | bolts/shift | 20 | 35 | 50 | S-070 |
| PRD.UM.007 | Cable bolt — drill, install, grout & plate | holes/shift | 10 | 20 | 30 | S-070 |
| PRD.UM.008 | Weldmesh & fibre-reinforced shotcrete to back / walls | m³/shift | 10 | 20 | 30 | S-070 |
| PRD.UM.009 | LHD bogging / loading to ore pass or truck | t/hr | 50 | 120 | 200 | S-070 |
| PRD.UM.010 | Backfill placement — paste / CAF / rockfill to mined void | m³/hr | 20 | 50 | 100 | S-070 |
| PRD.UM.011 | Ventilation ducting / layflat ventbag run — hang | m/shift | 100 | 250 | 500 | S-070 |
| PRD.UM.012 | Services reticulation — water/air pipe + power/comms cable | m/shift | 50 | 150 | 350 | S-070 |
| PRD.UM.013 | Secondary breaking / oversize reduction (rockbreaker) | t/hr | 20 | 50 | 120 | S-070 |
| PRD.UM.014 | Shaft furnishing — guides/buntons, services, ladderway | m/day | 1 | 3 | 6 | S-070 |