Underground mining

Load–haul–dump mucking to an ore pass

Underground mining
  1. Loader bucketMeasure accepted muck volume or tonnes on a consistent basis.
  2. Haul driveTravel, congestion and available ventilation affect cycles.
  3. Discharge pointReconcile dumped material to the receiving location.
Illustrative workfront for Load–haul–dump mucking to an ore pass.

Underground load–haul–dump loader

Compare direct LHD haul to an ore pass with short tramming to a truck transfer. Cross-section, gradient, passing bays and haul distance govern the fleet choice.

Supplier information to obtain

Request equipment envelope, verified payload, haul profile, ventilation allocation, traffic arrangements, tip availability and shift dispatch records.

Supporting plant and crew

LHD, tip or transfer infrastructure, service crew and truck where transfer is selected. Keep separate allowances for drawpoint and haul route availability.

Epiroc identifies the Scooptram ST7 as an underground loader. Epiroc Scooptram ST7 specification

Construction method

Release the workfront

Confirm work-area release and match the dump point to the haul route before allocating operating time.

Execute the work

Time loading, loaded travel and discharge, then return and reposition. Record delays at interacting equipment separately.

Measure and hand over

Reconcile delivered tonnes with payload records and destinations. Development advance needs additional excavation, ground support and services cycles.

Productivity calculator

Use measured tonnes per bucket, allowing for fill and material density. Separate haul distances and avoid applying a delay factor already captured in timed cycles.

Example values demonstrate the arithmetic. Use shift records, supplier programmes or a measured trial for an estimate.

Calculation basis and shift treatment

One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.

Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.

Productivity evidence

LHD bogging / loading to ore pass or truck

Low 50 · Typical 120 · High 200   t/hr

Compare the same haul distance, tip arrangement, payload and treatment of operating delays.

PRD.UM.009 · Vaultix source S-070 · Indicative internal benchmark

Related methodologies

The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.

Discipline work packages and survey requirements