Supplier information to obtain
Request equipment envelope, verified payload, haul profile, ventilation allocation, traffic arrangements, tip availability and shift dispatch records.
Compare direct LHD haul to an ore pass with short tramming to a truck transfer. Cross-section, gradient, passing bays and haul distance govern the fleet choice.
Request equipment envelope, verified payload, haul profile, ventilation allocation, traffic arrangements, tip availability and shift dispatch records.
LHD, tip or transfer infrastructure, service crew and truck where transfer is selected. Keep separate allowances for drawpoint and haul route availability.
Epiroc identifies the Scooptram ST7 as an underground loader. Epiroc Scooptram ST7 specification
Confirm work-area release and match the dump point to the haul route before allocating operating time.
Time loading, loaded travel and discharge, then return and reposition. Record delays at interacting equipment separately.
Reconcile delivered tonnes with payload records and destinations. Development advance needs additional excavation, ground support and services cycles.
Use measured tonnes per bucket, allowing for fill and material density. Separate haul distances and avoid applying a delay factor already captured in timed cycles.
One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Low 50 · Typical 120 · High 200 t/hr
Compare the same haul distance, tip arrangement, payload and treatment of operating delays.
PRD.UM.009 · Vaultix source S-070 · Indicative internal benchmark
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.