Onshore wind
- Crawler craneSetup, relocation and workable lifting windows govern the programme.
- Tower sectionTrack each component and connection release.
- Crane hardstandVerify access and the released working area before mobilisation.
Construction and release sequence
- Release heavy-haul access, crane pads and foundation survey
- Place foundation, anchor cage and tower interfaces
- Erect tower, nacelle and blades within the approved lift windows
- Release collector circuits, commissioning records and turbine handover
Work packages and conformance checks
Heavy-Haul Access Roads, Hardstands & Crane PadsSurvey swept-path geometry, grades, pad footprint and crossfall against the heavy-haul and crane design.Collector Network, Grid Connection & CommissioningSurvey collector routes, joint bays, switchgear interfaces and metering asset locations.Turbine Supply & Erection — tower, nacelle, hub & blades (the big lift)Check tower flange setting, tower alignment and component interface geometry at the nominated stage.WTG Foundations — gravity (mass-concrete) & piled turbine basesCheck anchor cage position, bolt projection, ring level and foundation centre before and after the pour.
Production and measurement
Separate pad construction, crane relocation, component lifts, weather standby and grid release.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.WF.001 | Heavy-haul access track construct — oversize swept-path geometry + bearing | m/day per crew | 150 | 300 | 500 | S-301 |
| PRD.WF.002 | Engineered crane hardstand per turbine — to main-crane ground-bearing pressure | days/pad | 3 | 6 | 12 | S-301 |
| PRD.WF.003 | Turbine component / blade laydown area per turbine | days/turbine | 1 | 2 | 4 | S-301 |
| PRD.WF.004 | WTG foundation excavation & subgrade preparation | days/foundation | 1 | 2 | 4 | S-301 |
| PRD.WF.005 | Gravity (mass-concrete) WTG foundation — place & cure (per foundation) | days/foundation | 5 | 10 | 20 | S-301 |
| PRD.WF.006 | Piled WTG foundation (poor ground) — piles + cap | days/foundation | 4 | 8 | 16 | S-301 |
| PRD.WF.007 | Anchor cage / foundation ring set to mm tower-interface tolerance | days/foundation | 1 | 2 | 4 | S-301 |
| PRD.WF.008 | Tower-section erection — sections lifted, aligned & bolted | sections/crane-day | 2 | 3 | 5 | S-301/218 |
| PRD.WF.009 | Nacelle & hub heavy single lift (weather/wind-window bound) | lifts/crane-day | 0.3 | 0.7 | 1.5 | S-301/218 |
| PRD.WF.010 | Blade install (single-blade / bunny-ear / pre-assembled) | blades/crane-day | 1 | 2 | 3 | S-301/218 |
| PRD.WF.011 | Main + tailing crane mobilise, assemble & walk/relocate between pads | days/mobilisation | 5 | 12 | 25 | S-301/218 |
| PRD.WF.012 | Inter-array MV collector cable — trench & direct-bury lay | m/day per crew | 150 | 300 | 600 | S-301 |
| PRD.WF.013 | Turbine commissioning + power-curve / performance verification | turbines/week | 1 | 2 | 4 | S-301 |
| PRD.WF.014 | Weather-lost-day factor on big-lift erection (achieved / calendar) | factor | 0.5 | 0.7 | 0.9 | S-301 |
Construction references
- Onshore Wind Farm Construction