Onshore wind

Verify haul access and hardstands, release foundation and anchor geometry, erect turbine components, then hand over collector and turbine test packs.

Onshore wind
  1. Crawler craneSetup, relocation and workable lifting windows govern the programme.
  2. Tower sectionTrack each component and connection release.
  3. Crane hardstandVerify access and the released working area before mobilisation.
Illustrative workfront within Onshore wind.
Open the Wind turbine tower-section erection calculator

Construction and release sequence

  1. Release heavy-haul access, crane pads and foundation survey
  2. Place foundation, anchor cage and tower interfaces
  3. Erect tower, nacelle and blades within the approved lift windows
  4. Release collector circuits, commissioning records and turbine handover

Work packages and conformance checks

Production and measurement

Separate pad construction, crane relocation, component lifts, weather standby and grid release.

View the discipline reference figureOnshore wind reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.WF.001Heavy-haul access track construct — oversize swept-path geometry + bearingm/day per crew150300500S-301
PRD.WF.002Engineered crane hardstand per turbine — to main-crane ground-bearing pressuredays/pad3612S-301
PRD.WF.003Turbine component / blade laydown area per turbinedays/turbine124S-301
PRD.WF.004WTG foundation excavation & subgrade preparationdays/foundation124S-301
PRD.WF.005Gravity (mass-concrete) WTG foundation — place & cure (per foundation)days/foundation51020S-301
PRD.WF.006Piled WTG foundation (poor ground) — piles + capdays/foundation4816S-301
PRD.WF.007Anchor cage / foundation ring set to mm tower-interface tolerancedays/foundation124S-301
PRD.WF.008Tower-section erection — sections lifted, aligned & boltedsections/crane-day235S-301/218
PRD.WF.009Nacelle & hub heavy single lift (weather/wind-window bound)lifts/crane-day0.30.71.5S-301/218
PRD.WF.010Blade install (single-blade / bunny-ear / pre-assembled)blades/crane-day123S-301/218
PRD.WF.011Main + tailing crane mobilise, assemble & walk/relocate between padsdays/mobilisation51225S-301/218
PRD.WF.012Inter-array MV collector cable — trench & direct-bury laym/day per crew150300600S-301
PRD.WF.013Turbine commissioning + power-curve / performance verificationturbines/week124S-301
PRD.WF.014Weather-lost-day factor on big-lift erection (achieved / calendar)factor0.50.70.9S-301