Supplier information to obtain
Request component schedule, engineered lift studies, pad design, road geometry, wind criteria, rigging list and relocation sequence from the lift contractor.
Compare a travelling crawler with dismantle-and-transfer arrangements. Check the proposed configuration against the heaviest component at its actual radius and elevation.
Request component schedule, engineered lift studies, pad design, road geometry, wind criteria, rigging list and relocation sequence from the lift contractor.
Main and assist cranes, section transport, rigging and bolting crews. Include crane build, ballast movements, moves between turbines and weather standby.
Liebherr describes a narrow-track travel configuration intended for wind farm assembly. Liebherr LR 1700-1.0W
Release foundation and hardstand, confirm component arrivals and allocate preparation and crane assembly separately.
Rig and upend the tower section, place it, complete the required connection and release the rigging. Identify crew activities that tie up the crane.
Record sections accepted by section type. Programme nacelle and blade lifts separately because their geometry and weather windows differ.
Use a section class with comparable geometry. Enter the workable hours for that class once. Keep crane travel and turbine-to-turbine moves outside the repeat lift.
One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Low 2 · Typical 3 · High 5 sections/crane-day
The reference counts tower sections per crane-day. Crane relocation, blade lifts and weather treatment can change the comparison.
PRD.WF.008 · Vaultix source S-301/218 · Indicative internal benchmark
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.