Bridges

Precast girder erection by launching gantry

Bridges and structures
  1. Launching gantryMoving and setting the gantry contributes to each erection cycle.
  2. GirderTrack each fabricated beam from delivery to its accepted position.
  3. Bearing seatSurvey seat position and level before releasing the span.
Illustrative workfront for Precast girder erection by launching gantry.

Bridge beam launching gantry

Compare gantry launch with ground-based cranes where access, traffic or waterways constrain crane pads. Repetition can offset gantry assembly and relocation time.

Supplier information to obtain

Request beam mass and geometry, pier spacing, deck curvature, delivery route, bearing release, support reactions and proposed launch sequence.

Supporting plant and crew

Gantry, beam transporter, bearing and survey crews, setup cranes and temporary supports. Reserve access for beam delivery independently of launch time.

DEAL distinguishes beam launchers, segmental erection equipment and full-span systems. DEAL launching and erection systems

Construction method

Release the workfront

Verify the approved erection design, pier release and beam delivery sequence. Schedule gantry assembly and proof checks separately.

Execute the work

Receive each girder, transfer and place it, then survey and secure the unit before releasing the gantry.

Measure and hand over

Record beams accepted per span. Include gantry advance between spans, deck closures and removal in the programme.

Productivity calculator

Use one girder per batch. Divide span-specific advance time by the number of girders only for repetitive spans. Model atypical end spans separately.

Example values demonstrate the arithmetic. Use shift records, supplier programmes or a measured trial for an estimate.

Calculation basis and shift treatment

One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.

Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.

Productivity evidence

Use the linked discipline reference and obtain a measured cycle for this specific configuration. The work package has no adopted numerical benchmark.

Related methodologies

The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.

Discipline work packages and survey requirements

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.