Supplier information to obtain
Request beam mass and geometry, pier spacing, deck curvature, delivery route, bearing release, support reactions and proposed launch sequence.
Compare gantry launch with ground-based cranes where access, traffic or waterways constrain crane pads. Repetition can offset gantry assembly and relocation time.
Request beam mass and geometry, pier spacing, deck curvature, delivery route, bearing release, support reactions and proposed launch sequence.
Gantry, beam transporter, bearing and survey crews, setup cranes and temporary supports. Reserve access for beam delivery independently of launch time.
DEAL distinguishes beam launchers, segmental erection equipment and full-span systems. DEAL launching and erection systems
Verify the approved erection design, pier release and beam delivery sequence. Schedule gantry assembly and proof checks separately.
Receive each girder, transfer and place it, then survey and secure the unit before releasing the gantry.
Record beams accepted per span. Include gantry advance between spans, deck closures and removal in the programme.
Use one girder per batch. Divide span-specific advance time by the number of girders only for repetitive spans. Model atypical end spans separately.
One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Use the linked discipline reference and obtain a measured cycle for this specific configuration. The work package has no adopted numerical benchmark.
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.