Supplier information to obtain
Request pipe diameter, wall thickness, string geometry, lifting study, equipment configuration, trench release and inspection arrangements.
Compare conventional open-trench lowering with trenchless crossings at constrained locations. Split the estimate by string length, terrain, crossing method and access.
Request pipe diameter, wall thickness, string geometry, lifting study, equipment configuration, trench release and inspection arrangements.
Matched sideboom spread, pipe handling gear, padding equipment, survey crew and coating inspection. Align trench, welding and reinstatement crews across separate fronts.
Caterpillar identifies the PL87 as a dedicated pipelayer. Caterpillar PL87 pipelayer
Release the trench and accepted welded string. Confirm inspection and delivery clearances before allocating the spread.
Position the spread, lower the accepted string, inspect placement and release for padding. Separate moves around crossings and short tie-ins.
Record metres lowered. Welding, testing, backfill and reinstatement are separate activities in the complete mainline programme.
Enter the released string length and the occupation time of the whole spread. Adding pipelayers changes the lift arrangement and does not multiply the string output.
One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Low 300 · Typical 600 · High 1200 m/day
The mainline benchmark covers stringing through backfill. The calculator measures the lowering spread alone.
PRD.OG.001 · Vaultix source S-065 · Indicative internal benchmark
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.