Supplier information to obtain
Request the mix dispatch profile, truck payload and return cycle, feeder geometry, paving width and roller pattern for the nominated lift.
Compare direct tipping with a material transfer vehicle where truck changes interrupt the paver. Check space for the combined train and transitions at intersections.
Request the mix dispatch profile, truck payload and return cycle, feeder geometry, paving width and roller pattern for the nominated lift.
Delivery fleet, transfer vehicle, paver, breakdown and finish rollers. Match tonnage delivered to the mass the paving and rolling crews can accept.
Vögele describes the feeder as the machine transferring mix from trucks to the paver. Vögele MT 3000-5 Standard
Release the surface and work zone, agree lot boundaries and reconcile lift thickness, width and compacted density with the tonnage.
Observe batch arrivals, actual paving output and completed rolling coverage over the same strip. Keep the three crews independent in the model.
Survey the finished lot and reconcile accepted area with weighbridge dockets. Price joints, tapers and remobilisations separately.
Use a truckload or a measured tonnage block. Convert accepted area to tonnes using compacted thickness in metres × density in t/m³. Enter fleet delivery interval, not a single truck round trip.
Independent resources process successive equal batches. Enter the elapsed productive time from startup to the first accepted batch separately. Each later batch completes at the slowest stage interval. This assumes sufficient buffer space, steady supply and no shared resources. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Low 300 · Typical 600 · High 1100 m2/hr (at 40 mm lift)
The reference is area per hour for a 40 mm wearing course. Convert both sides to a common thickness, density and time basis.
PRD.PV.013 · Vaultix source S-061 · Indicative internal benchmark
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.