Roads

Continuous asphalt paving train

Roads and pavements
  1. Material transferContinuity of mix delivery determines how often the paver stops.
  2. ScreedMeasure paving width and thickness against the issued layer design.
  3. RollerThe compaction train must keep up with the paving front.
Illustrative workfront for Continuous asphalt paving train.

Asphalt material transfer vehicle

Compare direct tipping with a material transfer vehicle where truck changes interrupt the paver. Check space for the combined train and transitions at intersections.

Supplier information to obtain

Request the mix dispatch profile, truck payload and return cycle, feeder geometry, paving width and roller pattern for the nominated lift.

Supporting plant and crew

Delivery fleet, transfer vehicle, paver, breakdown and finish rollers. Match tonnage delivered to the mass the paving and rolling crews can accept.

Vögele describes the feeder as the machine transferring mix from trucks to the paver. Vögele MT 3000-5 Standard

Construction method

Release the workfront

Release the surface and work zone, agree lot boundaries and reconcile lift thickness, width and compacted density with the tonnage.

Execute the work

Observe batch arrivals, actual paving output and completed rolling coverage over the same strip. Keep the three crews independent in the model.

Measure and hand over

Survey the finished lot and reconcile accepted area with weighbridge dockets. Price joints, tapers and remobilisations separately.

Productivity calculator

Use a truckload or a measured tonnage block. Convert accepted area to tonnes using compacted thickness in metres × density in t/m³. Enter fleet delivery interval, not a single truck round trip.

Example values demonstrate the arithmetic. Use shift records, supplier programmes or a measured trial for an estimate.

Calculation basis and shift treatment

Independent resources process successive equal batches. Enter the elapsed productive time from startup to the first accepted batch separately. Each later batch completes at the slowest stage interval. This assumes sufficient buffer space, steady supply and no shared resources. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.

Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.

Productivity evidence

Asphalt AC10 wearing course - by thickness (m2)

Low 300 · Typical 600 · High 1100   m2/hr (at 40 mm lift)

The reference is area per hour for a 40 mm wearing course. Convert both sides to a common thickness, density and time basis.

PRD.PV.013 · Vaultix source S-061 · Indicative internal benchmark

Related methodologies

The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.

Discipline work packages and survey requirements