Supplier information to obtain
Request the pile schedule, tolerance envelope, rig mast and tooling compatibility, refusal procedure, trial results and row access width.
Compare driven piles, predrilled installation and ground screws against trial results. Divide the array by ground conditions, slope, refusal incidence and pile family.
Request the pile schedule, tolerance envelope, rig mast and tooling compatibility, refusal procedure, trial results and row access width.
Pile rig, telehandler, set-out and verification crew, and a predrill rig where required. Plan steel distribution before the driver enters each row.
Vermeer identifies the PD10R as a remote-controlled pile driver for solar installation. Vermeer PD10R
Release survey control and trial pile results. Stage the correct lengths by tracker row and keep material supply ahead of the rig.
Move to the mark, pitch and drive, then check position and head level. Measure rejected piles and approved remediation separately.
Release accepted posts to tracker assembly. Compare daily rig records with accepted counts by ground zone.
Use one post per batch. Enter an observed cycle for its soil zone. Keep refusal recovery time with affected rows instead of applying it to the whole site.
One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Low 120 · Typical 250 · High 450 no/rig-day
Compare accepted posts per rig-day in comparable ground. Agree treatment of refusal and rework.
PRD.SF.001 · Vaultix source S-303 · Indicative internal benchmark
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.