Substations

Transformer transfer and set on plinth

Substations
  1. Modular transporterAllow for the transfer route, setup and final positioning.
  2. TransformerMaintain the equipment identity through delivery and placement.
  3. PlinthConfirm the surveyed set-down position and civil release.
Illustrative workfront for Transformer transfer and set on plinth.

Self-propelled modular transporter

Compare direct crane placement with modular transport and jack-and-slide where yard clearance or access restricts the approach.

Supplier information to obtain

Request transport mass and centre of gravity, route envelope, axle loading, plinth elevation and the approved transfer arrangement.

Supporting plant and crew

SPMT, hydraulic jacks, slide tracks, survey and specialist heavy-haul crew. Separate line-haul and yard positioning quotations.

Buckingham records transferring to an SPMT for a confined yard, followed by jack-and-slide placement. Buckingham transformer transport case

Construction method

Release the workfront

Release access and the plinth. Confirm the delivery configuration and receiving window with the transporter and transformer supplier.

Execute the work

Receive onto the yard transporter, position at the plinth, then transfer and survey the final set. Allow temporary track installation and removal.

Measure and hand over

Record a mechanically placed transformer. Accessories, oil treatment, cabling, testing and energisation each have a separate handover.

Productivity calculator

Use one transformer per batch and the specialist installation schedule. Compute installation shift equivalents only. Road transport, commissioning and waiting for outages sit outside the set cycle.

Example values demonstrate the arithmetic. Use shift records, supplier programmes or a measured trial for an estimate.

Calculation basis and shift treatment

One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.

Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.

Productivity evidence

Heavy-haul, offload & set transformer onto plinth (whole operation)

Low 2 · Typical 5 · High 10   days/transformer

The reference includes heavy haul, offload and set. The calculator starts at yard transfer. Reconcile scope before comparing duration.

PRD.SS.015 · Vaultix source S-065 · Indicative internal benchmark

Related methodologies

The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.

Discipline work packages and survey requirements

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.