Supplier information to obtain
Request transport mass and centre of gravity, route envelope, axle loading, plinth elevation and the approved transfer arrangement.
Compare direct crane placement with modular transport and jack-and-slide where yard clearance or access restricts the approach.
Request transport mass and centre of gravity, route envelope, axle loading, plinth elevation and the approved transfer arrangement.
SPMT, hydraulic jacks, slide tracks, survey and specialist heavy-haul crew. Separate line-haul and yard positioning quotations.
Buckingham records transferring to an SPMT for a confined yard, followed by jack-and-slide placement. Buckingham transformer transport case
Release access and the plinth. Confirm the delivery configuration and receiving window with the transporter and transformer supplier.
Receive onto the yard transporter, position at the plinth, then transfer and survey the final set. Allow temporary track installation and removal.
Record a mechanically placed transformer. Accessories, oil treatment, cabling, testing and energisation each have a separate handover.
Use one transformer per batch and the specialist installation schedule. Compute installation shift equivalents only. Road transport, commissioning and waiting for outages sit outside the set cycle.
One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Low 2 · Typical 5 · High 10 days/transformer
The reference includes heavy haul, offload and set. The calculator starts at yard transfer. Reconcile scope before comparing duration.
PRD.SS.015 · Vaultix source S-065 · Indicative internal benchmark
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.