Supplier information to obtain
Request measured payloads, loaded and empty travel times by haul profile, spotting time, available truck count and dump or crusher service rate.
Compare rigid trucks on maintained haul roads with articulated trucks on softer construction access. Match truck size to shovel passes and the receiving point.
Request measured payloads, loaded and empty travel times by haul profile, spotting time, available truck count and dump or crusher service rate.
Mining shovel or wheel loader, rigid trucks, road grader, water cart and dump support. Record queueing separately from free-running travel.
Caterpillar presents mining shovels and haul trucks as a matched loading and hauling system. Caterpillar loading and hauling systems
Split haul routes by distance, grade and material. Use weighbridge or dispatch tonnes per truck and available fleet count.
Match shovel load interval, fleet return interval and receiving interval on one payload basis. Use a full truck cycle divided by operating trucks for fleet capacity.
Reconcile tonnes delivered to dispatch. Convert to bank volume only with measured in-situ density for the material domain.
Use one observed payload as the batch. If truck cycle includes queueing caused by the shovel or crusher, use a queue-free cycle to estimate unconstrained fleet capacity or retain achieved fleet data and document it.
Independent resources process successive equal batches. Enter the elapsed productive time from startup to the first accepted batch separately. Each later batch completes at the slowest stage interval. This assumes sufficient buffer space, steady supply and no shared resources. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Use the linked discipline reference and obtain a measured cycle for this specific configuration. The work package has no adopted numerical benchmark.
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.