Tunnels

Segmentally lined EPB tunnel drive

Tunnels and underground works
  1. CutterheadGround conditions and interventions affect the boring cycle.
  2. ShieldSeparate excavation time from stoppages and maintenance.
  3. Segment ringSurvey the ring and reconcile accepted advance.
Illustrative workfront for Segmentally lined EPB tunnel drive.

Earth pressure balance tunnel boring machine

Compare EPB, slurry shield and open hard-rock options against the ground model and groundwater conditions. Price interventions and shaft logistics by reach.

Supplier information to obtain

Obtain a drive schedule with ring length, ground domains, planned maintenance, segment delivery capacity and muck handling capacity.

Supporting plant and crew

Shield and backup train, segment erector, grout equipment, spoil conveyor or trains and shaft crane. Identify shared shaft time.

The Rio project illustrates how ground conditions influence excavation mode and spoil conveyance. Herrenknecht EPB shield project

Construction method

Release the workfront

Release launch works and confirm a steady supply of segments, grout and spoil capacity before starting the production allowance.

Execute the work

Measure excavation time and ring build time separately. Allocate service extensions or recurring interruptions to each ring on the same basis.

Measure and hand over

Reconcile completed chainage to accepted rings and survey. Treat assembly, launch, interventions and retrieval as separate programme activities.

Productivity calculator

Use actual ring width as the batch quantity. For the selected sequential cycle, enter only servicing that stops advance. Split the estimate where the machine changes mode.

Example values demonstrate the arithmetic. Use shift records, supplier programmes or a measured trial for an estimate.

Calculation basis and shift treatment

One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.

Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.

Productivity evidence

EPB/slurry advance, urban soft ground, single shield

Low 8 · Typical 12 · High 18   m/day

The reference includes a full day of drive production. Compare with the number and length of shifts actually rostered.

PRD.TU.001 · Vaultix source S-065 · Indicative internal benchmark

Related methodologies

The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.

Discipline work packages and survey requirements