Plant and crew
Work barge, lifting frame, handling crew and ROV or dive inspection under the approved marine plan; include grout spread for fabric forms.
Marine works / Scour protection
Set units to the released filter or prepared bed, complete joints and pile transitions, then inspect alignment and edge restraint.
Work barge, lifting frame, handling crew and ROV or dive inspection under the approved marine plan; include grout spread for fabric forms.
Measure net protected area. Separate fabricated overlaps, special closures, lifting moves and any grout quantities from net area.
| Record | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.MAR.037 | Place articulated concrete mattress | m2/day | 100 | 300 | 600 | S-065 |
| PRD.MAR.038 | Grout-bag / fabric-form mattress around piles (diver-assisted) | m2/day | 30 | 80 | 150 | S-065 |
Indicative planning bands. Match material, vessel and scope. Establish the source roster before converting a day, shift or week to productive hours.
Record corners, joints, lifted edges and pile interfaces by cell. Supplement sounding coverage with georeferenced underwater inspection.
Inspector releases installed unit IDs and continuity evidence to the final scour survey.
Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.
Incoming release · Geotextile or granular scour filter
Feeds · Scour profile and underwater acceptance
Open this row in the lot worksheetTake quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.