Roads / Rehabilitation

Cold milling and reclaimed asphalt removal

Estimate in m² milled.

Cold Planer (Milling Machine)
  1. Enclosed milling rotorThe 2.01 m rotor cuts beneath this side plate. Pass depth and effective width determine the volume removed.
  2. Front discharge conveyorThe primary belt feeds the folding discharge conveyor. It loads reclaimed asphalt into the truck ahead.
  3. Crawler unitsThe near-side pair is visible here. Four steerable crawler units support the chassis and position the machine between passes.
Plant reference for Cold milling and reclaimed asphalt removal Compare the Caterpillar PM620 reference and photographs ↗

Construction method and plant

Mark milling depths and tie-ins, profile in planned passes, load recovered asphalt and sweep. Inspect the exposed surface.

Plant and crew

Cold planer, cartage trucks, sweeper and survey crew. Match milling width and depth to available fleet and closure.

Measure and release the lot

Quantity take-off

Measure plan area by depth band. Estimate reclaimed tonnes from area × removed thickness × existing density and reconcile dockets.

Handover record

Release the inspected milled lot or direct local failures to patching before overlay.

The source band excludes RAP cartage or disposal. Track queueing, pass count and disposal location separately.

Where this package fits

Productivity references

Reference activitySource unitLowTypicalHighSource
PRD.PV.018
Profiling / cold planing - shallow (<=50 mm)
m2/hr (at <=50 mm depth)3007001300S-061
PRD.PV.019
Profiling / cold planing - deep / full-depth (>100 mm, multi-pass)
m2/hr (multi-pass to full depth)150400800S-061

Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.

Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.

Survey conformance and lot release

Observe
Compare milled levels and tie-in depths with the rehabilitation profile by pass.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Release the inspected milled lot or direct local failures to patching before overlay.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.