Supplier information to obtain
Check table sizes and weights, turning paths, transfer opening, floor capacity, form inventory and available crane or lifting-system time.
Use table forms on repetitive open floor plates. Compare handset or panelised forms for short runs, irregular bays, stairs and transfer floors.
Check table sizes and weights, turning paths, transfer opening, floor capacity, form inventory and available crane or lifting-system time.
Table sets and trolleys, vertical transfer system or tower crane, edge protection and survey crew. Book lifting time shared with reinforcement deliveries.
Doka identifies separate equipment for horizontal table movement and transfer between levels. Doka table shifting devices
Divide the floor into pour zones and confirm the stripping and reshoring release for the preceding level.
Strip and shift a released table, transfer between levels, then align and survey it. Keep infill and edge forms as separate quantities.
Record accepted soffit contact area. Reinforcing, embedments, concrete, curing and release determine the complete floor programme.
Enter contact area per table or repeated table group. Model the form-moving crew only. Add infill and structural release intervals to the floor programme.
One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Low 25 · Typical 45 · High 70 m2/crew-day
The reference covers erection and stripping of soffit formwork. The model covers table movement. Use actual table area and separate infill work.
PRD.BS.006 · Vaultix source S-065 · Indicative internal benchmark
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.