Repeat-floor table formwork

Buildings and electrical services
  1. Table formRepetition depends on striking, moving and resetting each table.
  2. Shifting trolleyAllow for travel and handling access between slab bays.
  3. Floor bayLink survey and concrete records to the released pour area.
Illustrative workfront for Repeat-floor table formwork.

Tableform shifting trolley

Use table forms on repetitive open floor plates. Compare handset or panelised forms for short runs, irregular bays, stairs and transfer floors.

Supplier information to obtain

Check table sizes and weights, turning paths, transfer opening, floor capacity, form inventory and available crane or lifting-system time.

Supporting plant and crew

Table sets and trolleys, vertical transfer system or tower crane, edge protection and survey crew. Book lifting time shared with reinforcement deliveries.

Doka identifies separate equipment for horizontal table movement and transfer between levels. Doka table shifting devices

Construction method

Release the workfront

Divide the floor into pour zones and confirm the stripping and reshoring release for the preceding level.

Execute the work

Strip and shift a released table, transfer between levels, then align and survey it. Keep infill and edge forms as separate quantities.

Measure and hand over

Record accepted soffit contact area. Reinforcing, embedments, concrete, curing and release determine the complete floor programme.

Productivity calculator

Enter contact area per table or repeated table group. Model the form-moving crew only. Add infill and structural release intervals to the floor programme.

Example values demonstrate the arithmetic. Use shift records, supplier programmes or a measured trial for an estimate.

Calculation basis and shift treatment

One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.

Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.

Productivity evidence

Formwork/falsework erect + strip (soffit form to deck)

Low 25 · Typical 45 · High 70   m2/crew-day

The reference covers erection and stripping of soffit formwork. The model covers table movement. Use actual table area and separate infill work.

PRD.BS.006 · Vaultix source S-065 · Indicative internal benchmark

Related methodologies

The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.

Discipline work packages and survey requirements

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.