Marine works / Scour protection

Rock armour placement around piles and toes

Graded rock armour and its filter around the steel pile interfaces.
  1. Rock armourReconcile placed tonnes with the surveyed layer profile.
  2. Pile interfaceInspect transitions and gaps around the pile group.
  3. Placement spreadRock supply and reach affect the production window.
Lot measurement
accepted t placed
Method reference
MAR-SCOUR-001
Construction routes
3

Work sequence and plant spread

Place the approved grading by cell, build toe and transitions, and retain access to the pile group and adjacent works.

Plant and crew

Rock barge and grab or long-reach shore excavator, survey launch and delivery fleet. Separate land-based and floating spreads.

Quantity and productivity

Use accepted tonnes and reconcile to the designed footprint and layer profile. Measure operating output after positioning and rock supply interruptions.

RecordActivitySource unitLowTypicalHighSource key
PRD.MAR.035Place rock rip-rap scour protection (land-based)t/day3007001500S-065
PRD.MAR.036Place rip-rap from barge (around piles)t/day150400800S-065

Indicative planning bands. Match material, vessel and scope. Establish the source roster before converting a day, shift or week to productive hours.

Survey checks and lot handover

Survey conformance

Survey toe, crest, perimeter and as-placed surface. Compare against filter survey for thickness where both surfaces have adequate coverage.

Release record and receiver

Scour lead submits cell placement and delivery records for final profile inspection; mark thin areas for correction.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.