Marine works / Scour protection

Scour material qualification and supply

Graded rock armour and its filter around the steel pile interfaces.
  1. Rock armourReconcile placed tonnes with the surveyed layer profile.
  2. Pile interfaceInspect transitions and gaps around the pile group.
  3. Placement spreadRock supply and reach affect the production window.
Lot measurement
accepted t delivered
Method reference
MAR-SCOUR-001
Construction routes
3

Work sequence and plant spread

Confirm grading, durability and stone class. Segregate filter, underlayer and armour, then track delivery lots to the intended protection cells.

Plant and crew

Quarry sorting and weighing plant, stockpile crew, road or barge transport and material inspector.

Quantity and productivity

Use certified tonnes by grade. Check supply-and-stockpile output against rock-placement demand; record rejected or rehandled material separately.

Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.

Survey checks and lot handover

Survey conformance

Survey stockpile boundaries where quantity reconciliation requires it. Carry grading certificates, load dockets and destination cell IDs into the placement plan.

Release record and receiver

Materials lead releases each graded stockpile and delivery allocation to the placing spread.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.