Plant and crew
Quarry sorting and weighing plant, stockpile crew, road or barge transport and material inspector.
Marine works / Scour protection
Confirm grading, durability and stone class. Segregate filter, underlayer and armour, then track delivery lots to the intended protection cells.
Quarry sorting and weighing plant, stockpile crew, road or barge transport and material inspector.
Use certified tonnes by grade. Check supply-and-stockpile output against rock-placement demand; record rejected or rehandled material separately.
Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.
Survey stockpile boundaries where quantity reconciliation requires it. Carry grading certificates, load dockets and destination cell IDs into the placement plan.
Materials lead releases each graded stockpile and delivery allocation to the placing spread.
Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.
Incoming release · Marine control and berth access
Feeds · Geotextile or granular scour filter · Rock armour placement around piles and toes
Open this row in the lot worksheetIncoming release · Marine control and berth access
Feeds · Geotextile or granular scour filter · Rock armour placement around piles and toes
Open this row in the lot worksheetIncoming release · Marine control and berth access
Feeds · Geotextile or granular scour filter
Open this row in the lot worksheetTake quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.