Marine works / Piling

Bored marine piles and rock sockets

Marine rotary rig working through a casing from a jack-up platform.
  1. Rotary drill rigBoring and cleaning time depend on the founding material and tooling.
  2. Jack-up platformAllow for positioning, set-up and moving between pile groups.
  3. Pile casing and boreTie depth, founding checks and concrete quantities to the pile ID.
Lot measurement
completed bored piles
Method reference
MAR-PILE-001
Construction routes
1

Work sequence and plant spread

Set casing on the released coordinates, log the excavation and socket, inspect the base under the approved method, lower the cage and place concrete.

Plant and crew

Jack-up or suitable drill platform, rotary rig, casing, spoil handling, cage lift and tremie supply. Separate soil and rock domains.

Quantity and productivity

Use the whole-pile shift band or build up drilling metres, cage and concrete time. Adding the component bands to a whole-pile duration duplicates work.

RecordActivitySource unitLowTypicalHighSource key
PRD.MAR.006Bored marine pile in soil, 1200-1500 mm dia (drill+cage+tremie)no/shift0.512S-065
PRD.MAR.007Rock-socket advance (medium-strong rock)m/hr0.30.81.5S-065
PRD.MAR.008Tremie concrete placement, marine bored pilem3/hr101830S-065

Indicative planning bands. Match material, vessel and scope. Establish the source roster before converting a day, shift or week to productive hours.

Survey checks and lot handover

Survey conformance

Check casing centre and verticality, depth reference, socket termination and cage top. Reconcile concrete placement and integrity records by pile.

Release record and receiver

Piling lead provides bore log, founding acceptance, cage and concrete records, integrity evidence and surveyed pile group for head works.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.

Where this lot fits

Source records

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.