Plant and crew
Jack-up or suitable drill platform, rotary rig, casing, spoil handling, cage lift and tremie supply. Separate soil and rock domains.
Marine works / Piling
Set casing on the released coordinates, log the excavation and socket, inspect the base under the approved method, lower the cage and place concrete.
Jack-up or suitable drill platform, rotary rig, casing, spoil handling, cage lift and tremie supply. Separate soil and rock domains.
Use the whole-pile shift band or build up drilling metres, cage and concrete time. Adding the component bands to a whole-pile duration duplicates work.
| Record | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.MAR.006 | Bored marine pile in soil, 1200-1500 mm dia (drill+cage+tremie) | no/shift | 0.5 | 1 | 2 | S-065 |
| PRD.MAR.007 | Rock-socket advance (medium-strong rock) | m/hr | 0.3 | 0.8 | 1.5 | S-065 |
| PRD.MAR.008 | Tremie concrete placement, marine bored pile | m3/hr | 10 | 18 | 30 | S-065 |
Indicative planning bands. Match material, vessel and scope. Establish the source roster before converting a day, shift or week to productive hours.
Check casing centre and verticality, depth reference, socket termination and cage top. Reconcile concrete placement and integrity records by pile.
Piling lead provides bore log, founding acceptance, cage and concrete records, integrity evidence and surveyed pile group for head works.
Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.
Incoming release · Pile delivery, gate and template set-out
Feeds · Pile cut-off, plugs and cap release
Open this row in the lot worksheetTake quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.