Marine works / Piling

Pile cut-off, plugs and cap release

Floating crane, driving hammer and guide frame at a tubular pile group.
  1. Crawler craneInclude positioning and pile handling in the spread cycle.
  2. Driving hammerLink installation and founding records to the individual pile.
  3. Guide frameVerify position and inclination before releasing the pile group.
Lot measurement
pile heads released
Method reference
MAR-PILE-001
Construction routes
2

Work sequence and plant spread

Review the as-installed group, trim heads to issued levels, prepare the connection or place the designed plug. Resolve eccentricities before cap formwork.

Plant and crew

Marine access platform, cutting and handling crew, cleaning plant and concrete pump where the design requires a plug.

Quantity and productivity

Count heads by detail. Convert a plug-only m³/h band to time from plug volume and carry access, trim, cleaning and cure separately.

RecordActivitySource unitLowTypicalHighSource key
PRD.MAR.005Tremie/pump concrete plug to driven tubularm3/hr81525S-065

Indicative planning bands. Match material, vessel and scope. Establish the source roster before converting a day, shift or week to productive hours.

Survey checks and lot handover

Survey conformance

Survey cut-off level, head coordinates, connection orientation and plug level where applicable. Compare the group with the cap interface drawing.

Release record and receiver

Structural reviewer releases the pile-head register and reviewed connection detail to the cap and scour leads.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.

Where this lot fits

Source records