Marine works / Piling

Pile delivery, gate and template set-out

Floating crane, driving hammer and guide frame at a tubular pile group.
  1. Crawler craneInclude positioning and pile handling in the spread cycle.
  2. Driving hammerLink installation and founding records to the individual pile.
  3. Guide frameVerify position and inclination before releasing the pile group.
Lot measurement
released pile groups
Method reference
MAR-PILE-001
Construction routes
2

Work sequence and plant spread

Check pile identification and condition. Position the gate to the design grid, record the working offsets and release the pitch locations.

Plant and crew

Crane barge or jack-up, steel gate or template, survey instruments and handling crew. Sequence delivered piles by bent and length.

Quantity and productivity

Count setups by pile group. Time moves and checks, keeping repeated pitching within the production cycle where already included.

Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.

Survey checks and lot handover

Survey conformance

Independently observe gate position and orientation, pile centres and intended rake from shore control. Check again after a platform move.

Release record and receiver

Surveyor releases the group set-out and pile schedule to the installation lead.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.