Plant and crew
Over-water forms or precast shells, reinforcement crew, crane, pump and concrete supply. Include form access, hold points and stripping.
Marine works / Wharf construction
Set forms from the accepted pile group, verify connection reinforcement and embeds, place the pour and protect it until the specified strength release.
Over-water forms or precast shells, reinforcement crew, crane, pump and concrete supply. Include form access, hold points and stripping.
Take concrete by cap geometry; estimate reinforcement separately only where excluded from the cap spread. Add cure and inspection waits by pour lot.
| Record | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.MAR.009 | In-situ pile cap / headstock concrete over water (form, fix, pour) | m3/day | 8 | 20 | 40 | S-065 |
| PRD.MAR.012 | Reinforcement fixing, marine deck/cap | t/day per gang | 1 | 2.5 | 4 | S-065 |
Indicative planning bands. Match material, vessel and scope. Establish the source roster before converting a day, shift or week to productive hours.
Check cap centre, seat elevations, bolt or dowel layout and finished bearing line. Link each observation to the pile group and pour ID.
Structural lead issues strength evidence, bearing-seat survey and cap release before deck-unit erection.
Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.
Incoming release · Pile cut-off, plugs and cap release
Feeds · Precast wharf deck units
Open this row in the lot worksheetIncoming release · Pile cut-off, plugs and cap release
Feeds · Precast wharf deck units
Open this row in the lot worksheetTake quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.