Marine works / Dredging

Reclamation bund and receiving cell

Cutter suction dredger, cutter ladder and floating discharge pipeline.
  1. Cutter headMaterial and swing advance govern excavation at the face.
  2. Dredge pontoonTrack working time separately from moves and interruptions.
  3. Discharge lineThe line and receiving cell must accept the dredger’s output.
Lot measurement
m³ of accepted bund
Method reference
MAR-DREDGE-001
Construction routes
1

Work sequence and plant spread

Set out containment and outlets, construct the designed bund, verify storage and discharge arrangements, then release the cell to the pump crew.

Plant and crew

Rock trucks or barges, excavator, dozer and survey crew. Include decant and monitoring equipment specified for the cell.

Quantity and productivity

Measure accepted bund sections between surveyed surfaces. Assess rock supply, spreading and compaction as separate constraints.

RecordActivitySource unitLowTypicalHighSource key
PRD.MAR.018Rock bund constructionm3/day3008001500S-065

Indicative planning bands. Match material, vessel and scope. Establish the source roster before converting a day, shift or week to productive hours.

Survey checks and lot handover

Survey conformance

Survey toe, crest, outlet and receiving area in a common datum. Verify the available fill footprint and stage level.

Release record and receiver

Reclamation lead signs the cell readiness plan and receiving capacity before hydraulic placement begins.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.

Where this lot fits

Source records