Marine works / Dredging

Cutter suction dredge and hydraulic placement

Cutter suction dredger, cutter ladder and floating discharge pipeline.
  1. Cutter headMaterial and swing advance govern excavation at the face.
  2. Dredge pontoonTrack working time separately from moves and interruptions.
  3. Discharge lineThe line and receiving cell must accept the dredger’s output.
Lot measurement
in-situ m³ dredged
Method reference
MAR-DREDGE-001
Construction routes
1

Work sequence and plant spread

Release the cut and receiving cell together. Dredge and pump concurrently, move the discharge point as required and record stoppages and material zones.

Plant and crew

Cutter suction dredger, discharge pipeline, booster if specified, workboat and reclamation cell crew. Match pump duty and receiver capacity to the cut.

Quantity and productivity

Use the lower bank-equivalent output of excavation, pumping and reception. Record placed fill separately by survey. The placement comparator uses a different quantity basis.

RecordActivitySource unitLowTypicalHighSource key
PRD.MAR.013CSD in soft-medium material (in-situ m3)m3/week3000080000200000S-065
PRD.MAR.017Hydraulic fill placement (pumped from CSD)m3/week3000090000250000S-065

Indicative planning bands. Match material, vessel and scope. Establish the source roster before converting a day, shift or week to productive hours.

Survey checks and lot handover

Survey conformance

Compare pre- and post-dredge bed surfaces and track fill levels within the receiving cell. Document the conversion basis for any material balance.

Release record and receiver

Dredge lead hands over cut-cell records. Reclamation lead hands over placed-fill surveys, discharge logs and environmental records for independent review.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.