Marine works / Dredging

Pre-dredge hydrographic survey

Hydrographic survey launch over the berth survey area.
  1. Positioning mastRecord the positioning and datum checks used for the survey.
  2. Survey launchLine speed, turns and access determine field time.
  3. Survey transducerVerify sensor offsets and corrections before accepting the reduced soundings.
Lot measurement
accepted ha surveyed
Method reference
MAR-DREDGE-001
Construction routes
6

Work sequence and plant spread

Agree the pay polygon and survey order, acquire baseline soundings, validate offsets and corrections, then freeze the accepted surface version.

Plant and crew

Survey launch, multibeam or specified sounder, GNSS, motion sensor, sound-velocity equipment and processing team. Allow for obstruction shadows and infill lines.

Quantity and productivity

Use net hectares on the accepted grid. Derive field time from planned line length and achieved line speed, adding turns, cross-lines and processing.

Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.

Survey checks and lot handover

Survey conformance

Check water-level correction, sound velocity, positioning, coverage and reported uncertainty. Agree common boundaries and grid resolution for the final comparison.

Release record and receiver

Hydrographer issues raw and reduced data, metadata, baseline surface and coverage plot to the dredge superintendent and quantity surveyor.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.