Marine crane, hammer, template, handling crew and supply barge. Select floating or jack-up spread against the approved installation arrangement.
Marine works / Piling
Pitch the identified pile, check position and rake, install to the approved founding criteria and record interruptions and splices. Review departures before trimming.
Marine crane, hammer, template, handling crew and supply barge. Select floating or jack-up spread against the approved installation arrangement.
Split counts by length, founding domain and platform type. Measure pitch, install, splice and reposition time; match the Vaultix comparator to the whole cycle.
| Record | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.MAR.001 | Drive large-dia steel tubular pile (<=914 mm) to set, jack-up, good ground | no/shift | 2 | 4 | 6 | S-065 |
| PRD.MAR.002 | Drive large-dia steel tubular pile, floating barge (swell-limited) | no/shift | 1 | 2.5 | 4 | S-065 |
Indicative planning bands. Match material, vessel and scope. Establish the source roster before converting a day, shift or week to productive hours.
Observe the as-driven centre and inclination at known elevations. Tie the installation record, toe evidence and head observation to the unique pile ID.
Piling engineer releases the as-driven group with installation logs, splice inspection and disposition of refusal or position departures.
Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.
Incoming release · Pile delivery, gate and template set-out
Feeds · Pile cut-off, plugs and cap release
Open this row in the lot worksheetTake quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.