Marine works / Dredging

Barge cycle and spoil reception readiness

Backhoe dredger and hopper barge at the dredge face. Illustrative plant spread.
  1. Bucket and cut faceMeasure the accepted in-situ cut against the agreed dredge surfaces.
  2. Backhoe pontoonAllow for repositioning and the workable tide window.
  3. Hopper bargePayload and round-trip time can limit the excavator’s productive rate.
Lot measurement
haul spreads commissioned
Method reference
MAR-DREDGE-001
Construction routes
3

Work sequence and plant spread

Confirm dispatch sequence, receiver acceptance and contingency destination. Measure load, outward sail, discharge, return and positioning from a representative cycle.

Plant and crew

Split-hopper barges or scows, tug, tracking system and receiving crew. Match allowable loaded condition and receiver service time to the dredger.

Quantity and productivity

Fleet limit in bank m³/h = operating vessels × accepted bank-equivalent payload ÷ full cycle hours. Restrict dredger output to this limit. Charge production cartage once within the dredge spread or a separate cost item.

Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.

Survey checks and lot handover

Survey conformance

Verify navigation track and placement area. Document the basis for converting loose payload to in-situ quantity, with density or bulking evidence.

Release record and receiver

Logistics lead releases vessel IDs, payload basis, working cycle and approved reception location. Voyage and disposal records accompany the closing survey.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.