Marine works / Common works

Marine spread mobilisation and positioning

Piled wharf bay, floating crane and exposed seabed armour. Illustrative workfront.
  1. Precast deckDeck units span between headstocks. Keep the open bay available for scour placement and inspection.
  2. Steel pilesThe accepted pile-head group releases the cap and scour crews.
  3. Crane pontoonVessel access and positioning determine which bay the lifting spread can serve.
Lot measurement
spread setups
Method reference
MAR-PILE-001
Construction routes
6

Work sequence and plant spread

Mobilise the nominated fleet to the access area. Establish its working position and confirm deck configuration, interfaces and planned relocations.

Plant and crew

Tug, workboat, pontoon or jack-up, deck crane, mooring crew and surveyor. Include launch, tow, set-up and demobilisation in the agreed cost items.

Quantity and productivity

Count discrete primary setups. Time tow, site entry, positioning and release separately from planned weather standby.

Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.

Survey checks and lot handover

Survey conformance

Check platform position and orientation against marine control and the approved work envelope. Record offsets used by machine guidance.

Release record and receiver

Marine superintendent issues the vessel readiness record, position check and available working window to the operating crew.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.

Where this lot fits