Plant and crew
Shore survey team, survey launch, tide logger and marine coordinator. Agree vessel access and survey control before either production spread mobilises.
Marine works / Common works
Register berth limits, navigation windows, chart-to-project datum relationship and controlled drawings. Verify shore marks independently and issue the control sheet to both fleets.
Shore survey team, survey launch, tide logger and marine coordinator. Agree vessel access and survey control before either production spread mobilises.
Count released workfronts. Build hours from control transfer, independent checks and coordination of each access window.
Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.
Confirm grid, units, tide reference, benchmark levels and transformation using independent observations. Retain the closure and instrument checks.
Marine coordinator and survey lead issue the referenced control sheet and accessible footprint to dredge and pile leads.
Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.
Incoming release · Release the workfront boundaries and project controls.
Feeds · Pre-dredge hydrographic survey · Sediment classification and destination release · Marine spread mobilisation and positioning · Scour material qualification and supply
Open this row in the lot worksheetIncoming release · Release the workfront boundaries and project controls.
Feeds · Pre-dredge hydrographic survey · Sediment classification and destination release · Marine spread mobilisation and positioning · Scour material qualification and supply
Open this row in the lot worksheetIncoming release · Release the workfront boundaries and project controls.
Feeds · Pre-dredge hydrographic survey · Sediment classification and destination release · Marine spread mobilisation and positioning · Scour material qualification and supply
Open this row in the lot worksheetIncoming release · Release the workfront boundaries and project controls.
Feeds · Pre-dredge hydrographic survey · Sediment classification and destination release · Marine spread mobilisation and positioning
Open this row in the lot worksheetIncoming release · Release the workfront boundaries and project controls.
Feeds · Pre-dredge hydrographic survey · Sediment classification and destination release · Marine spread mobilisation and positioning
Open this row in the lot worksheetIncoming release · Release the workfront boundaries and project controls.
Feeds · Pre-dredge hydrographic survey · Marine spread mobilisation and positioning
Open this row in the lot worksheetTake quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.