Marine works / Common works

Marine control and berth access

Hydrographic survey launch over the berth survey area.
  1. Positioning mastRecord the positioning and datum checks used for the survey.
  2. Survey launchLine speed, turns and access determine field time.
  3. Survey transducerVerify sensor offsets and corrections before accepting the reduced soundings.
Lot measurement
released workfronts
Method reference
MAR-WHARF-001
Construction routes
6

Work sequence and plant spread

Register berth limits, navigation windows, chart-to-project datum relationship and controlled drawings. Verify shore marks independently and issue the control sheet to both fleets.

Plant and crew

Shore survey team, survey launch, tide logger and marine coordinator. Agree vessel access and survey control before either production spread mobilises.

Quantity and productivity

Count released workfronts. Build hours from control transfer, independent checks and coordination of each access window.

Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.

Survey checks and lot handover

Survey conformance

Confirm grid, units, tide reference, benchmark levels and transformation using independent observations. Retain the closure and instrument checks.

Release record and receiver

Marine coordinator and survey lead issue the referenced control sheet and accessible footprint to dredge and pile leads.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.

Where this lot fits