Roads / Roadside works

Road safety barriers and terminals

Estimate in m of installed barrier.

Traffic management and road furniture
  1. Protection vehicleInclude the setup, moves and standby for the active front.
  2. Traffic taperCheck the implemented layout against the approved staging plan.
  3. Safety barrierInspect the completed run and terminal before opening the lane.
Construction context for Road safety barriers and terminals

Construction method and plant

Set out offsets and terminal zones from the design. Confirm services and ground, install supports and rails or precast units, then inspect transitions.

Plant and crew

Post driver or drilling rig, handling vehicle and specialist installation crew. Match equipment to the barrier system and ground.

Measure and release the lot

Quantity take-off

Measure runs by system and ground class. Count terminals, anchors and transitions independently.

Handover record

Release chainage, offsets, terminal records and installation inspection to the commissioning register.

Drivable posts and cored footings have different outputs. Do not apply a linear rail rate to terminals.

Where this package fits

Productivity references

Reference activitySource unitLowTypicalHighSource
PRD.RF.001
W-beam guardrail install (drivable ground)
m/day90150220S-061
PRD.RF.002
W-beam guardrail install (rock / cored / bolted footings)
m/day4080120S-061
PRD.RF.003
Guardrail end terminal (crash-tested, MASH)
per day1.535S-061
PRD.RF.006
Concrete barrier - precast F-shape / single-slope (placed)
m/day60120200S-061

Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.

Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.

Survey conformance and lot release

Observe
Survey offsets, post heights, terminal positions and transitions relative to the finished road.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Release chainage, offsets, terminal records and installation inspection to the commissioning register.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.