Plant and crew
Post driver or drilling rig, handling vehicle and specialist installation crew. Match equipment to the barrier system and ground.
Estimate in m of installed barrier.
Set out offsets and terminal zones from the design. Confirm services and ground, install supports and rails or precast units, then inspect transitions.
Post driver or drilling rig, handling vehicle and specialist installation crew. Match equipment to the barrier system and ground.
Measure runs by system and ground class. Count terminals, anchors and transitions independently.
Release chainage, offsets, terminal records and installation inspection to the commissioning register.
Drivable posts and cored footings have different outputs. Do not apply a linear rail rate to terminals.
Incoming release · Shoulders, verges and tie-ins
Feeds · Lot reconciliation and reopening
Incoming release · Shoulders, verges and tie-ins
Feeds · Lot reconciliation and reopening
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.RF.001 W-beam guardrail install (drivable ground) | m/day | 90 | 150 | 220 | S-061 |
| PRD.RF.002 W-beam guardrail install (rock / cored / bolted footings) | m/day | 40 | 80 | 120 | S-061 |
| PRD.RF.003 Guardrail end terminal (crash-tested, MASH) | per day | 1.5 | 3 | 5 | S-061 |
| PRD.RF.006 Concrete barrier - precast F-shape / single-slope (placed) | m/day | 60 | 120 | 200 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.