Plant and crew
Grader, trucks, water cart and roller. Select smaller plant for narrow strips or constrained access.
Estimate in compacted m³.
Set shoulder and tie-in levels, place and compact suitable material, trim crossfall and check drainage at transitions.
Grader, trucks, water cart and roller. Select smaller plant for narrow strips or constrained access.
Sum shoulder lengths × applicable widths × compacted thickness. Treat tapers and sealed shoulder surfacing separately.
Release shoulder level, edge support and clear working width for barriers and guideposts.
Model one roadside at a time where staging reduces access. Avoid duplicating shoulder quantities in mainline pavement.
Incoming release · Unbound granular base
Feeds · Road safety barriers and terminals · Signs, supports and delineators · Lot reconciliation and reopening
Incoming release · Concrete joints, curing and traffic release
Feeds · Road safety barriers and terminals · Signs, supports and delineators · Lot reconciliation and reopening
Incoming release · In-situ pavement stabilisation
Feeds · Signs, supports and delineators · Lot reconciliation and reopening
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.PV.021 Shoulder gravel (supply + place + trim + compact) | m3/hr (placing crew) | 50 | 95 | 150 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.