Plant and crew
Excavator, lifting spread, bedding crew, compactors and survey. Select the lift arrangement by unit mass, reach and trench geometry.
Estimate in m of pipe barrel.
Set out the outlet and crossing. Excavate, prepare bedding, lay units to line and grade, and backfill in accepted lifts. Stage embankment interfaces at the design elevation.
Excavator, lifting spread, bedding crew, compactors and survey. Select the lift arrangement by unit mass, reach and trench geometry.
Sum barrel lengths for each run and diameter. Carry pits, headwalls, bedding and excavation in their own measurement units.
Provide invert survey, joint inspection and backfill release before the pavement crew crosses the trench.
Separate depth, groundwater, shoring and traffic staging. The DN600 laying band covers a particular pipe size and operation.
Incoming release · Service verification and protection · Clearing and topsoil stripping
Feeds · Embankment placement and compaction · Kerb, channel and pit interfaces
Incoming release · Clearing and topsoil stripping · Service verification and protection
Incoming release · Clearing and topsoil stripping · Service verification and protection
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.DR.006 RCP pipe lay DN600 | m/day | 30 | 50 | 65 | S-061 |
| PRD.DR.010 Bedding & haunch (Type 1 / Type 2) | m3/day placed | 20 | 40 | 60 | S-061 |
| PRD.DR.011 Backfill & compact (select / in-situ) | m3/day | 150 | 250 | 350 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.