Roads / Drainage

Cross drainage and culvert installation

Estimate in m of pipe barrel.

Drainage and stormwater
  1. ExcavatorExcavation and lifting access govern the installation front.
  2. Pipe beddingVerify support and invert before the pipe is covered.
  3. Pit connectionSurvey the inlet and outlet levels against the design.
Construction context for Cross drainage and culvert installation

Construction method and plant

Set out the outlet and crossing. Excavate, prepare bedding, lay units to line and grade, and backfill in accepted lifts. Stage embankment interfaces at the design elevation.

Plant and crew

Excavator, lifting spread, bedding crew, compactors and survey. Select the lift arrangement by unit mass, reach and trench geometry.

Measure and release the lot

Quantity take-off

Sum barrel lengths for each run and diameter. Carry pits, headwalls, bedding and excavation in their own measurement units.

Handover record

Provide invert survey, joint inspection and backfill release before the pavement crew crosses the trench.

Separate depth, groundwater, shoring and traffic staging. The DN600 laying band covers a particular pipe size and operation.

Where this package fits

Productivity references

Reference activitySource unitLowTypicalHighSource
PRD.DR.006
RCP pipe lay DN600
m/day305065S-061
PRD.DR.010
Bedding & haunch (Type 1 / Type 2)
m3/day placed204060S-061
PRD.DR.011
Backfill & compact (select / in-situ)
m3/day150250350S-061

Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.

DISC-DRAIN-METH-001 Pipe Culvert DrainageQueensland TMR specifications

Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.

Survey conformance and lot release

Observe
Observe each barrel invert, crossing alignment, joint and headwall before backfill.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Provide invert survey, joint inspection and backfill release before the pavement crew crosses the trench.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.