Roads / Enabling works

Clearing and topsoil stripping

Estimate in m³ in situ.

20 t Crawler Dozer
  1. BladePush distance and material condition influence production.
  2. TracksGround conditions affect traction and travel.
  3. RipperSeparate ripping time from pushing and spreading.
Plant reference for Clearing and topsoil stripping

Construction method and plant

Set out the approved footprint and install the applicable erosion controls. Strip by measured depth and haul reusable topsoil to the nominated stockpile.

Plant and crew

Dozer or excavator, haul units and environmental crew. Check stockpile reach and material segregation.

Measure and release the lot

Quantity take-off

Multiply surveyed footprint by stripping depth by zone. Track stockpiled, exported and reinstated volumes separately.

Handover record

Release exposed formation limits and surveyed stockpile quantities to earthworks and drainage crews.

Long leads, vegetation boundaries and double handling reduce output. Confirm the volume basis of the reference band.

Where this package fits

Productivity references

Reference activitySource unitLowTypicalHighSource
PRD.EW.001
Strip & stockpile topsoil
m3/hr120200320S-061

Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.

Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.

Survey conformance and lot release

Observe
Survey original and stripped surfaces over a common stripping footprint.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Release exposed formation limits and surveyed stockpile quantities to earthworks and drainage crews.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.