Roads / Earthworks

Embankment placement and compaction

Estimate in compacted m³.

20 t Crawler Dozer
  1. BladePush distance and material condition influence production.
  2. TracksGround conditions affect traction and travel.
  3. RipperSeparate ripping time from pushing and spreading.
Plant reference for Embankment placement and compaction

Construction method and plant

Prepare the receiving bench, spread in controlled lifts, condition moisture and compact. Keep lot boundaries visible to the test crew.

Plant and crew

Spreading dozer or grader, water cart, roller and testing crew. Match roller type and passes to the fill trial.

Measure and release the lot

Quantity take-off

Take compacted volume from the design surface difference. Convert to imported tonnes using an agreed density and reconcile deliveries.

Handover record

Record lift acceptance, level and material class. Release the next lift or formation trim for that chainage.

Distinguish purchased fill, excavated reuse and compacted output. Testing or water supply can control the shift.

Where this package fits

Productivity references

Reference activitySource unitLowTypicalHighSource
PRD.EW.014
Spread & level fill (place dumped material to grade)
m3/hr150300500S-061
PRD.EW.015
Compact fill - by layer (roller passes)
m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes)150300500S-061

Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.

DISC-EARTH-METH-001 Bulk Earthworks FormationQueensland TMR specifications

Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.

Survey conformance and lot release

Observe
Survey finished lift extents, level and batter geometry within each compaction lot.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Record lift acceptance, level and material class. Release the next lift or formation trim for that chainage.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.