Plant and crew
Spreading dozer or grader, water cart, roller and testing crew. Match roller type and passes to the fill trial.
Estimate in compacted m³.
Prepare the receiving bench, spread in controlled lifts, condition moisture and compact. Keep lot boundaries visible to the test crew.
Spreading dozer or grader, water cart, roller and testing crew. Match roller type and passes to the fill trial.
Take compacted volume from the design surface difference. Convert to imported tonnes using an agreed density and reconcile deliveries.
Record lift acceptance, level and material class. Release the next lift or formation trim for that chainage.
Distinguish purchased fill, excavated reuse and compacted output. Testing or water supply can control the shift.
Incoming release · Bulk cut and haul · Cross drainage and culvert installation
Feeds · Subsoil drains and outlets · Subgrade trim and proof roll
Incoming release · Bulk cut and haul · Cross drainage and culvert installation
Feeds · Subgrade trim and proof roll
Incoming release · Bulk cut and haul · Cross drainage and culvert installation
Feeds · Subgrade trim and proof roll
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.EW.014 Spread & level fill (place dumped material to grade) | m3/hr | 150 | 300 | 500 | S-061 |
| PRD.EW.015 Compact fill - by layer (roller passes) | m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) | 150 | 300 | 500 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.