Roads / Surfacing

Prime coat on prepared granular base

Estimate in m² primed.

20-Tonne Multi-Tyre Roller
  1. Pneumatic tyresPressure and ballast govern contact conditions.
  2. Ballast bodyConfirm the agreed working configuration.
  3. Operator stationAllow for turning and overlap in the rolling pattern.
Plant reference for Prime coat on prepared granular base

Construction method and plant

Clean the accepted base, apply the specified prime, record the spray area and protect it for the required release interval.

Plant and crew

Bitumen distributor, sweeper, supply tanker and protection crew. Confirm surface readiness and application design.

Measure and release the lot

Quantity take-off

Use net area by lot. Calculate litres against the specified application basis and record surplus separately.

Handover record

Release the primed surface after the specified absorption or curing interval and inspection.

Prime, primerseal and tack serve different interfaces. Select the treatment shown in the contract.

Where this package fits

Productivity references

Reference activitySource unitLowTypicalHighSource
PRD.PV.009
Prime coat (cutback / emulsion primer on unbound base)
m2/day (≈ 1,000-3,000 m2/hr)80001500025000S-061

Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.

Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.

Survey conformance and lot release

Observe
Survey the net primed lot area and register overlaps and exclusions against spray records.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Release the primed surface after the specified absorption or curing interval and inspection.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.