Plant and crew
Paver, feeder where required, haul fleet and roller train. Obtain mix dispatch, truck turnaround and compaction coverage.
Estimate in t placed.
Accept the supporting surface, sequence truck deliveries, pave the specified lift and complete compaction and joint treatment.
Paver, feeder where required, haul fleet and roller train. Obtain mix dispatch, truck turnaround and compaction coverage.
Area × compacted thickness × mix density gives planned tonnes. Reconcile delivered, rejected and accepted tonnes by lift.
Provide layer survey, compaction and lot release before tack and the wearing lift.
Separate thicknesses, mix designs and restricted runs. Use the existing asphalt-train calculator to test the controlling resource.
Test the paving train bottleneckIncoming release · Prime coat on prepared granular base
Feeds · Tack coat and asphalt interface
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.PV.015 Asphalt AC20 base/intermediate course - by thickness (m2) | m2/hr (at 60-70 mm lift) | 280 | 550 | 1000 | S-061 |
| PRD.PV.016 Asphalt - supply + lay + compact (tonnage basis) | t/hr (paver-and-crew limited; ≈ 350-650 t/day) | 40 | 60 | 85 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.