Plant and crew
Fine-trim grader, delivery fleet, roller and survey crew. Allow tighter finishing control than bulk fill.
Estimate in compacted m³.
Deliver compliant material to the released subbase, compact, trim to finished profile and inspect drainage paths and crossfall.
Fine-trim grader, delivery fleet, roller and survey crew. Allow tighter finishing control than bulk fill.
Sum compacted lift volumes. Track overbuild and trimming loss separately from accepted design quantity.
Release top-of-base survey, material tests and surface condition to the specified surfacing crew.
Short night possessions, trimming and correcting levels may govern the lot even with adequate quarry supply.
Incoming release · Unbound granular subbase
Incoming release · Unbound granular subbase
Feeds · Primerseal and holding period · Shoulders, verges and tie-ins
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.PV.004 Base unbound granular Type 2.1 / DGB20 (supply + place + compact) | m3/hr (placing crew, tighter tolerance) | 45 | 85 | 140 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.