Plant and crew
Auger or excavator, lifting vehicle, installation crew and survey. Match foundations and lifts to sign type.
Estimate in sign assemblies.
Confirm chainages and sight lines, construct supports and install approved faces. Inspect orientation and clearances.
Auger or excavator, lifting vehicle, installation crew and survey. Match foundations and lifts to sign type.
Count complete assemblies by size and posts. Take face area, foundations and delineators separately where the schedule splits them.
Record chainage, sign type, orientation and as-built evidence for the traffic switch.
Allow foundation curing and supplier lead time. A multi-post installation band may exclude sign-face supply.
Incoming release · Kerb, channel and pit interfaces
Feeds · Lot reconciliation and reopening
Incoming release · Shoulders, verges and tie-ins
Feeds · Lot reconciliation and reopening
Incoming release · Shoulders, verges and tie-ins
Feeds · Lot reconciliation and reopening
Incoming release · Shoulders, verges and tie-ins
Feeds · Lot reconciliation and reopening
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.RF.015 Regulatory / warning / guide sign on single post (<=2.2 m2) | per day | 8 | 18 | 30 | S-061 |
| PRD.RF.017 Large / multi-post guide sign (3-10 m2, 2-3 posts) | per day | 0.5 | 2 | 4 | S-061 |
| PRD.RF.009 Guideposts / delineators install | per day | 60 | 120 | 200 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.