Plant and crew
Calibrated binder spreader, recycler, water cart, grader and rollers. Select the train against the approved binder system.
Estimate in m² treated.
Release the treatment design and trial. Apply binder, mix the nominated depth, shape and compact inside the project working window, then protect and cure.
Calibrated binder spreader, recycler, water cart, grader and rollers. Select the train against the approved binder system.
Use treated width × length per pass, removing overlap from pay area. Derive binder demand from the approved application basis.
Issue treatment depth, spread records, test results and cure release before the overlying treatment.
Lime, cement and foamed bitumen have different production and curing constraints. Separate binder supply and remobilisation.
Incoming release · Local pavement repairs and tie-ins
Feeds · Primerseal and holding period · Shoulders, verges and tie-ins
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.PV.006 In-situ stabilisation - lime (spread + mix + compact + cure) | m2/day (≈ 250-600 m2/hr) | 2000 | 4000 | 7000 | S-061 |
| PRD.PV.007 In-situ stabilisation - cement (spread + mix + compact + cure) | m2/day (≈ 250-550 m2/hr) | 2000 | 3800 | 6500 | S-061 |
| PRD.PV.008 In-situ stabilisation - foamed bitumen (FBS, recycler) | m2/day (≈ 350-700 m2/hr) | 3000 | 5000 | 8500 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.