Roads / Pavement layers

In-situ pavement stabilisation

Estimate in m² treated.

Soil stabiliser and cold recycler
  1. Mixing drumDepth, width and passes determine treated volume.
  2. Wheel trainTravel speed depends on material and the specified treatment.
  3. Drum enclosureControl the mixing zone and reconcile accepted treatment area.
Plant reference for In-situ pavement stabilisation

Construction method and plant

Release the treatment design and trial. Apply binder, mix the nominated depth, shape and compact inside the project working window, then protect and cure.

Plant and crew

Calibrated binder spreader, recycler, water cart, grader and rollers. Select the train against the approved binder system.

Measure and release the lot

Quantity take-off

Use treated width × length per pass, removing overlap from pay area. Derive binder demand from the approved application basis.

Handover record

Issue treatment depth, spread records, test results and cure release before the overlying treatment.

Lime, cement and foamed bitumen have different production and curing constraints. Separate binder supply and remobilisation.

Where this package fits

Productivity references

Reference activitySource unitLowTypicalHighSource
PRD.PV.006
In-situ stabilisation - lime (spread + mix + compact + cure)
m2/day (≈ 250-600 m2/hr)200040007000S-061
PRD.PV.007
In-situ stabilisation - cement (spread + mix + compact + cure)
m2/day (≈ 250-550 m2/hr)200038006500S-061
PRD.PV.008
In-situ stabilisation - foamed bitumen (FBS, recycler)
m2/day (≈ 350-700 m2/hr)300050008500S-061

Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.

Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.

Survey conformance and lot release

Observe
Record treatment width, overlap limits and depth evidence for each recycler run.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Issue treatment depth, spread records, test results and cure release before the overlying treatment.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.