Plant and crew
Distributor, chip spreader, aggregate trucks, rollers and broom. Match chip supply to the spray run.
Estimate in m² primersealed.
Prepare and inspect the granular base, apply the approved binder and cover aggregate, roll and sweep. Manage the holding interval and traffic.
Distributor, chip spreader, aggregate trucks, rollers and broom. Match chip supply to the spray run.
Measure sealed plan area once. Estimate binder and cover aggregate separately from the final seal quantities.
Record spray sheets and surface condition, then release for the final seal or designated overlay.
Confirm whether the design calls for a primerseal or prime. Allow return visits and holding-period maintenance where specified.
Incoming release · Unbound granular base
Feeds · Sprayed bituminous seal
Incoming release · In-situ pavement stabilisation
Feeds · Sprayed bituminous seal
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.PV.010 Primer seal (primer binder + cover aggregate, 1 coat) | m2/day (≈ 800-2,500 m2/hr) | 6000 | 12000 | 20000 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.