Plant and crew
Form and concrete crew, pump, graded fill deliveries and compaction plant. Coordinate staging with the wall engineer.
Marine works / Quay wall
Place retained fill and drainage in the authorised stages, inspect anchors before concealment and cast the coping and embedded fittings.
Form and concrete crew, pump, graded fill deliveries and compaction plant. Coordinate staging with the wall engineer.
Measure coping length; derive pour volume and accepted fill by zone. Account for stage restrictions and shared access with berth dredging.
Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.
Survey coping face, crest, embed positions and adjacent fill surface. Attach movement records and concealed-work inspections.
Wall lead releases the coping and retained-side lot for fittings and final berth survey.
Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.
Incoming release · Quay walers, anchors and staged dredge release
Feeds · Fenders, panels and berth-face interfaces · Bollards, mooring fittings and deck services
Open this row in the lot worksheetTake quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.