Marine works / Quay wall

Quay coping, retained fill and edge completion

Quay wall beside the berth pocket, with landward restraint and retained fill.
  1. Quay wall and walerCheck wall alignment and restraint connections before the next excavation stage.
  2. Landward anchorageRecord the accepted anchor system and the stage it releases.
  3. Berth pocketSurvey the pocket against the approved deepening stage and surface.
Lot measurement
m of quay completed
Method reference
DISC-MARINE-METH-003
Construction routes
1

Work sequence and plant spread

Place retained fill and drainage in the authorised stages, inspect anchors before concealment and cast the coping and embedded fittings.

Plant and crew

Form and concrete crew, pump, graded fill deliveries and compaction plant. Coordinate staging with the wall engineer.

Quantity and productivity

Measure coping length; derive pour volume and accepted fill by zone. Account for stage restrictions and shared access with berth dredging.

Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.

Survey checks and lot handover

Survey conformance

Survey coping face, crest, embed positions and adjacent fill surface. Attach movement records and concealed-work inspections.

Release record and receiver

Wall lead releases the coping and retained-side lot for fittings and final berth survey.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.