Dredge acceptance and high-spot closeout

Hydrographic survey launch over the berth survey area.
  1. Positioning mastRecord the positioning and datum checks used for the survey.
  2. Survey launchLine speed, turns and access determine field time.
  3. Survey transducerVerify sensor offsets and corrections before accepting the reduced soundings.
Lot measurement
accepted dredge cells
Method reference
MAR-DREDGE-001
Construction routes
5

Work sequence and plant spread

Survey the finished pocket, identify exceptions, agree any local recut and resurvey the affected footprint before closing the cell.

Plant and crew

Survey launch, processing crew, quantity surveyor and local rework spread where needed.

Quantity and productivity

Compare the agreed baseline and final surfaces inside the pay mask. Keep high spots, payable overdepth and material outside limits separately identifiable.

Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.

Survey checks and lot handover

Survey conformance

Report least depth or highest bed elevation on the specified datum, coverage, uncertainty, boundary treatment and excluded shadows. Reconcile destination records.

Release record and receiver

Hydrographer and reviewer issue the accepted bathymetric surface and volume report to piling, scour or port operations as applicable.

Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.