Plant and crew
Concrete pump, delivery fleet, reinforcement and finishing crew, surveyor and testers. Confirm access and weather window for each pour.
Marine works / Wharf construction
Inspect deck units, fix the detailed reinforcement and cast-ins, place and finish the topping, then cure and verify the released loading stage.
Concrete pump, delivery fleet, reinforcement and finishing crew, surveyor and testers. Confirm access and weather window for each pour.
Use net deck area × thickness for theoretical concrete volume; count thickened zones separately. Price return visits, cure and strength waits per pour.
| Record | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.MAR.011 | In-situ topping deck pour (pump from deck) | m2/day | 60 | 150 | 300 | S-065 |
| PRD.MAR.012 | Reinforcement fixing, marine deck/cap | t/day per gang | 1 | 2.5 | 4 | S-065 |
Indicative planning bands. Match material, vessel and scope. Establish the source roster before converting a day, shift or week to productive hours.
Check deck line and level, crossfall, drainage lows, edge face and cast-in positions. Reconcile survey with concrete test and pour records.
Structural lead releases the deck load stage and as-built surface to berth furniture, services and operations.
Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.
Incoming release · Precast wharf deck units
Feeds · Fenders, panels and berth-face interfaces · Bollards, mooring fittings and deck services
Open this row in the lot worksheetIncoming release · Precast wharf deck units
Feeds · Fenders, panels and berth-face interfaces · Bollards, mooring fittings and deck services
Open this row in the lot worksheetTake quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.