Plant and crew
Crane barge or jack-up, pile gate, driving equipment and survey. Identify combi-wall king-pile and intermediate sheet sequences.
Marine works / Quay wall
Pitch and install the designed wall elements to the required founding and interlock arrangement. Monitor line throughout the panel and record obstructions.
Crane barge or jack-up, pile gate, driving equipment and survey. Identify combi-wall king-pile and intermediate sheet sequences.
Measure wall face area on the agreed depth basis. Count king piles or special closures separately where the schedule requires it.
| Record | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.MAR.004 | Pitch & vibrate steel sheet pile (combi/anchored wall) | m2/shift | 40 | 80 | 140 | S-065 |
Indicative planning bands. Match material, vessel and scope. Establish the source roster before converting a day, shift or week to productive hours.
Survey wall line, head elevation and inclination. Tie pile length and installation records to embedment evidence and interlock inspection.
Wall engineer releases the accepted panel to walers and anchors, with a drawing of unresolved deviations.
Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.
Incoming release · Pre-dredge hydrographic survey · Marine spread mobilisation and positioning
Feeds · Quay walers, anchors and staged dredge release · Marine steel corrosion protection
Open this row in the lot worksheetTake quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.