Roads / Formation

Select-fill capping layer

Estimate in compacted m³.

16-Tonne Motor Grader
  1. MouldboardCut width and pass count determine grading effort.
  2. Front axleTurning space and manoeuvres affect productive time.
  3. Rear tandemGround and haul traffic affect traction and finish.
Plant reference for Select-fill capping layer

Construction method and plant

Release the formation, deliver approved select fill, spread the specified lift and trim after compaction.

Plant and crew

Haul fleet, grader, roller and water cart. Check material source and moisture condition.

Measure and release the lot

Quantity take-off

Use lot area × compacted thickness. Price delivered tonnes with a documented density and moisture basis.

Handover record

Provide level and density records for the top of capping before the next pavement layer.

Use where the pavement design calls for capping. Separate undercut replacement from uniform capping.

Where this package fits

Productivity references

Reference activitySource unitLowTypicalHighSource
PRD.PV.002
Capping / select-fill layer (supply + place + compact)
m3/hr (placing crew)60110170S-061

Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.

Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.

Survey conformance and lot release

Observe
Compare the accepted formation and capping surfaces to verify compacted lift thickness.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Provide level and density records for the top of capping before the next pavement layer.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.