Plant and crew
Haul fleet, grader, roller and water cart. Check material source and moisture condition.
Estimate in compacted m³.
Release the formation, deliver approved select fill, spread the specified lift and trim after compaction.
Haul fleet, grader, roller and water cart. Check material source and moisture condition.
Use lot area × compacted thickness. Price delivered tonnes with a documented density and moisture basis.
Provide level and density records for the top of capping before the next pavement layer.
Use where the pavement design calls for capping. Separate undercut replacement from uniform capping.
Incoming release · Subgrade trim and proof roll
Feeds · Unbound granular subbase
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.PV.002 Capping / select-fill layer (supply + place + compact) | m3/hr (placing crew) | 60 | 110 | 170 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.