Roads / Pavement layers

Unbound granular subbase

Estimate in compacted m³.

16-Tonne Motor Grader
  1. MouldboardCut width and pass count determine grading effort.
  2. Front axleTurning space and manoeuvres affect productive time.
  3. Rear tandemGround and haul traffic affect traction and finish.
Plant reference for Unbound granular subbase

Construction method and plant

Confirm substrate release and material compliance. Place and moisture-condition each lift, compact and trim, then test the lot.

Plant and crew

Truck delivery fleet, grader or spreader, water cart and compaction train. Balance quarry dispatch with lift acceptance.

Measure and release the lot

Quantity take-off

Area × compacted lift thickness gives placed volume. Use separate areas for widening, tapers and intersections.

Handover record

Release level, thickness and test results to base placement, stabilisation or rigid pavement works.

A 150 mm area band applies only to that lift basis. Include haul once in the supplying or placing spread.

Where this package fits

Productivity references

Reference activitySource unitLowTypicalHighSource
PRD.PV.003
Sub-base unbound granular Type 2.3 (supply + place + compact)
m3/hr (placing crew)55100160S-061
PRD.PV.005
Unbound base/sub-base - per m2 basis (150 mm compacted lift)
m2/hr (at 150 mm lift)3506501100S-061

Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.

Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.

Survey conformance and lot release

Observe
Check subbase surface levels, crossfall and lift thickness at matching survey stations.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Release level, thickness and test results to base placement, stabilisation or rigid pavement works.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.