Plant and crew
Truck delivery fleet, grader or spreader, water cart and compaction train. Balance quarry dispatch with lift acceptance.
Estimate in compacted m³.
Confirm substrate release and material compliance. Place and moisture-condition each lift, compact and trim, then test the lot.
Truck delivery fleet, grader or spreader, water cart and compaction train. Balance quarry dispatch with lift acceptance.
Area × compacted lift thickness gives placed volume. Use separate areas for widening, tapers and intersections.
Release level, thickness and test results to base placement, stabilisation or rigid pavement works.
A 150 mm area band applies only to that lift basis. Include haul once in the supplying or placing spread.
Incoming release · Select-fill capping layer
Feeds · Unbound granular base · Kerb, channel and pit interfaces
Incoming release · Subgrade trim and proof roll
Feeds · Unbound granular base
Incoming release · Subgrade trim and proof roll
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.PV.003 Sub-base unbound granular Type 2.3 (supply + place + compact) | m3/hr (placing crew) | 55 | 100 | 160 | S-061 |
| PRD.PV.005 Unbound base/sub-base - per m2 basis (150 mm compacted lift) | m2/hr (at 150 mm lift) | 350 | 650 | 1100 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.