Plant and crew
Grader, water cart, roller, nominated proof-roll vehicle and test crew. Allow space for inspection.
Estimate in m² released.
Trim to design grade and crossfall, condition and compact the formation, then inspect the nominated lot. Map soft areas for treatment and retest.
Grader, water cart, roller, nominated proof-roll vehicle and test crew. Allow space for inspection.
Measure accepted formation area once. Record failed areas and treatment quantities separately.
Issue formation survey and lot acceptance before covering it. Unreleased areas remain separate workfronts.
Proof-roll coverage and preparation output have different scopes. Keep rectification and retesting visible.
Incoming release · Embankment placement and compaction · Subsoil drains and outlets
Feeds · Select-fill capping layer
Incoming release · Embankment placement and compaction
Feeds · Unbound granular subbase
Incoming release · Embankment placement and compaction
Feeds · Unbound granular subbase
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.PV.001 Subgrade preparation & trim (top of formation) | m2/hr | 200 | 450 | 800 | S-061 |
| PRD.PV.020 Pavement compaction / proof roll (acceptance) | m2/hr | 1500 | 3000 | 5000 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.