Roads / Surfacing

Sprayed bituminous seal

Estimate in m² finished seal.

20-Tonne Multi-Tyre Roller
  1. Pneumatic tyresPressure and ballast govern contact conditions.
  2. Ballast bodyConfirm the agreed working configuration.
  3. Operator stationAllow for turning and overlap in the rolling pattern.
Plant reference for Sprayed bituminous seal

Construction method and plant

Release the substrate treatment, spray and spread to the approved seal design, roll, sweep and record each run and coat.

Plant and crew

Distributor, chip spreader, aggregate trucks, pneumatic rollers and broom. Plan tanker and aggregate replenishment.

Measure and release the lot

Quantity take-off

Measure the footprint once for a complete two-coat item. Compute coat-specific binder litres and aggregate quantities.

Handover record

Release the finished seal following inspection, sweeping and the project traffic conditions.

A two-coat production band already includes two passes. Include delayed sweeping and traffic management in the correct package.

Where this package fits

Productivity references

Reference activitySource unitLowTypicalHighSource
PRD.PV.011
Sprayed seal - single/seal (14 mm, binder + cover aggregate)
m2/day (≈ 600-1,900 m2/hr)4000800015000S-061
PRD.PV.012
Sprayed seal - double/two-coat (14/7 mm)
m2/day (≈ 450-1,400 m2/hr, two passes)3000600011000S-061

Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.

Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.

Survey conformance and lot release

Observe
Survey the final seal footprint and confirm which coats occupy the same measured area.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Release the finished seal following inspection, sweeping and the project traffic conditions.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.