Plant and crew
Distributor, chip spreader, aggregate trucks, pneumatic rollers and broom. Plan tanker and aggregate replenishment.
Estimate in m² finished seal.
Release the substrate treatment, spray and spread to the approved seal design, roll, sweep and record each run and coat.
Distributor, chip spreader, aggregate trucks, pneumatic rollers and broom. Plan tanker and aggregate replenishment.
Measure the footprint once for a complete two-coat item. Compute coat-specific binder litres and aggregate quantities.
Release the finished seal following inspection, sweeping and the project traffic conditions.
A two-coat production band already includes two passes. Include delayed sweeping and traffic management in the correct package.
Incoming release · Primerseal and holding period
Feeds · Line marking and raised pavement markers · Lot reconciliation and reopening
Incoming release · Primerseal and holding period
Feeds · Line marking and raised pavement markers · Lot reconciliation and reopening
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.PV.011 Sprayed seal - single/seal (14 mm, binder + cover aggregate) | m2/day (≈ 600-1,900 m2/hr) | 4000 | 8000 | 15000 | S-061 |
| PRD.PV.012 Sprayed seal - double/two-coat (14/7 mm) | m2/day (≈ 450-1,400 m2/hr, two passes) | 3000 | 6000 | 11000 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.