Plant and crew
Excavator or dozer, trucks, grader and water cart. Match loader passes, truck cycles and receiving capacity.
Estimate in bank m³.
Classify cut by material and destination. Excavate, load and dispatch against a mass-haul schedule. Separate unsuitable material and spoil.
Excavator or dozer, trucks, grader and water cart. Match loader passes, truck cycles and receiving capacity.
Calculate bank volume from survey surfaces. Reconcile truck payloads using material density or a documented conversion to loose volume.
Give the fill crew the released material type and delivery profile. Issue cut-floor levels and disposal dockets.
Split short push, long haul and disposal. A band that includes cut-to-fill may overlap the separate fill spread.
Incoming release · Service verification and protection · Clearing and topsoil stripping
Incoming release · Clearing and topsoil stripping · Service verification and protection
Incoming release · Clearing and topsoil stripping · Service verification and protection
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.EW.002 Bulk excavation cut-to-fill (30t excavator + truck fleet) | m3/hr | 80 | 120 | 160 | S-061 |
| PRD.EW.003 Cut-to-spoil (excavator load-out, no on-site reuse) | m3/hr (loading limited) | 90 | 130 | 170 | S-061 |
| PRD.EW.007 Load & haul - 1 km one-way | m3/hr | 70 | 110 | 150 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.