Plant and crew
Survey launch, grab or backhoe and inspection team. Check access around piles and clearance for the placing vessel.
Marine works / Scour protection
Inspect bed condition, prepare the designated footprint and record any local variation in toe or transition geometry.
Survey launch, grab or backhoe and inspection team. Check access around piles and clearance for the placing vessel.
Measure the prepared polygon; take extra excavation by surveyed volume. Use actual cell preparation time and vessel moves.
Use the vessel or subcontractor programme, a trial or a comparable shift record. Retain accepted quantity, operating time, waiting time and spread composition with the adopted rate.
Observe the toe trench or preparation surface before filter placement. Show pile shadows, edges and coverage gaps for review.
Marine works lead releases the toe and base survey to the filter crew with marked exceptions.
Record the berth, cell, bent or panel ID, design revision, applicable tolerance, observation date, datum and verification method. Attach raw evidence, resolved departures and the designated reviewer’s disposition to the same lot.
Incoming release · Pile cut-off, plugs and cap release · Dredge acceptance and high-spot closeout
Feeds · Geotextile or granular scour filter
Open this row in the lot worksheetIncoming release · Pile cut-off, plugs and cap release · Dredge acceptance and high-spot closeout
Feeds · Geotextile or granular scour filter
Open this row in the lot worksheetIncoming release · Dredge acceptance and high-spot closeout · Quay walers, anchors and staged dredge release
Feeds · Geotextile or granular scour filter
Open this row in the lot worksheetIncoming release · Pre-dredge hydrographic survey · Marine spread mobilisation and positioning
Feeds · Geotextile or granular scour filter
Open this row in the lot worksheetTake quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.